Process piping Chapter  2 45


             2.5.6  Field bolt up of flanged joints by weight class
             Facility—Solar power plant

                  Man-hour per joint
                                              Pressure rating

                  Pipe size     150#/300#      600#/900#      1500#/2500#
                    0.5           1.00           1.20            1.60
                    0.75          1.00           1.20            1.60
                     1            1.00           1.20            1.60
                    1.5           1.00           1.20            1.60
                     2            1.00           1.20            1.60
                    2.5           1.00           1.25            1.63
                     3            1.20           1.50            1.95
                     4            1.60           2.00            2.60
                     6            2.40           3.00            3.90
                     8            3.20           4.00            5.20
                    10            4.00           5.00            6.50
                    12            4.80           6.00            7.80
                    14            5.60           7.00            9.10
                    16            6.40           8.00           10.40
                    18            7.20           9.00           11.70
                    20            8.00           10.00          13.00
                    24            9.60           12.00          15.60
                  Man-hours per joint to bolt-up valves, expansion joints, flanged fittings, and spools.