Page 78 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 78

Process piping Chapter  2 49


             2.7.1  Welding, carbon steel, and socket weld
             Facility—Industrial plant

                  Man-hour per SW
                                               Socket welds

                  Pipe size (inches)  Schedule 40 and 80  Schedule 100 and greater
                       0.5              1.2                 1.3
                       0.75             1.2                 1.3
                        1               1.3                 1.4
                       1.5              1.4                 1.6
                        2               1.5                 1.8
                  Includes place and fit up.


             2.7.2  Hydrostatic testing
             Facility—Industrial plant


             Man-hours per lineal foot
                                       Wall thickness in inches
              Pipe
                                                          00
              size  0.375 or less 0.406 –0.500 00  0.562 –0.688 00  0.718 –0.938 00  1.031 –1.219 00
                                                                      00
                                   00
                        00
                                               00
               0.5     0.022      0.028       0.034      0.042       0.060
              0.75     0.022      0.028       0.034      0.042       0.060
               1       0.022      0.028       0.034      0.042       0.060
               1.5     0.022      0.028       0.034      0.042       0.060
               2       0.022      0.028       0.034      0.042       0.060
               2.5     0.021      0.027       0.033      0.042       0.060
               3       0.025      0.032       0.040      0.050       0.072
               4       0.034      0.043       0.053      0.067       0.096
               6       0.050      0.065       0.079      0.101       0.144
               8       0.067      0.086       0.106      0.134       0.192
               10      0.084      0.108       0.132      0.168       0.240
               12      0.101      0.130       0.158      0.202       0.288
               14      0.118      0.151       0.185      0.235       0.336
               16      0.134      0.173       0.211      0.269       0.384
               18      0.151      0.194       0.238      0.302       0.432
               20      0.168      0.216       0.264      0.336       0.480
               24      0.202      0.259       0.317      0.403       0.576
             Man-hours to place/remove blinds, open/close valves, removal/replacement of valves and specialty items
             and pipe sections as required, and drain lines after testing.
   73   74   75   76   77   78   79   80   81   82   83