54  Industrial Process Plant Construction Estimating and Man-Hour Analysis


            2.8.3 Handle and install pipe, concrete, and vitrified clay
            2.8.3.1 Facility—Industrial plant (underground drainage piping)


                          Vitrified clay pipe           Concrete pipe
            Pipe size  Pipe set and align  Make-on  Pipe set align  Cement poured joint
             Inches       MH/LF       MH/JT      MH/LF           MH/JT

               4           0.08        0.32       0.07            0.24
               6           0.12        0.48       0.11            0.36
               8           0.16        0.64       0.14            0.48
               10          0.20        0.80       0.18            0.60
               12          0.24        0.96       0.22            0.72
               12          0.24        0.96       0.22            0.72
               16          0.32        1.28       0.29            0.96
               18          0.36        1.44       0.32            1.08
               20          0.40        1.60       0.36            1.20
               24          0.48        1.92       0.43            1.44
               30          0.60        2.40       0.54            1.80
               36          0.72        2.88       0.65            2.16
               42          0.84        3.36       0.76            2.52
               48          0.96        3.84       0.86            2.88
               60          1.20        4.80       1.08            3.60
            Pipe man-hours include handle, haul, place, and align in trench.


            2.8.4 Pipe trench—Machine, hand excavation, backfill, and
            sand bedding


            Pipe trench—machine and hand excavation
            Facility—industrial plant (underground drainage piping)
            Machine excavation                                   MH/CY
            Trench excavation—backhoe 1 CY bucket                 0.15
            Trench excavation—backhoe 3/4 CY bucket               0.20
            Trench excavation—backhoe 1/2 CY bucket               0.25
            Hand excavation
            Trench excavation—hand (to 4 deep)                    2.40
                                  0
            Pipe trench—backfill and compaction, loader and compactors, and hand and compactors
            Backfill and compaction                              MH/CY
            Backfill and compaction—loader and compactors         0.60
            Backfill and compaction—hand and compactors           3.40
            Pipe trench—sand bedding and shading with loader
                                                                 MH/CY
            Sand bedding and shading with loader                  0.40
            Pipe trench—shoring and bracing trenches
            Shoring (place/remove)                               MH/SF
            Laborer                                               5.50
            Carpenter                                             3.00