Process piping Chapter 2 53
2.8.1 Handle and install pipe and cast iron—Lead
and mechanical joint
Facility—Industrial plant (underground drainage piping)
Pipe size Pipe set and align Lead and mechanical joint Handle install fitting
Inches MH/LF MH/JT MH/EA
4 0.12 0.80 0.24
6 0.18 1.20 0.36
8 0.24 1.60 0.48
10 0.30 2.00 0.60
12 0.36 2.40 0.72
12 0.36 2.40 0.72
16 0.48 3.20 0.96
18 0.54 3.60 1.08
20 0.60 4.00 1.20
24 0.72 4.80 1.44
Pipe man-hours include handle, haul, place, and align in trench.
2.8.2 Handle and install pipe and cast iron soil—No hub
Facility—Industrial plant (underground drainage piping)
Pipe size Pipe set and align Handle install fitting Couplings
Inches MH/LF MH/EA MH/EA
4 0.10 0.24 0.40
6 0.15 0.36 0.60
8 0.20 0.48 0.80
10 0.25 0.60 1.00
12 0.30 0.72 1.20
12 0.30 0.72 1.20
16 0.40 0.96 1.60
18 0.45 1.08 1.80
20 0.50 1.20 2.00
24 0.60 1.44 2.40
Pipe man-hours include handle, haul, place, and align in trench.