Page 82 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 82

Process piping Chapter  2 53


             2.8.1  Handle and install pipe and cast iron—Lead
             and mechanical joint

             Facility—Industrial plant (underground drainage piping)

             Pipe size  Pipe set and align  Lead and mechanical joint  Handle install fitting

              Inches      MH/LF               MH/JT               MH/EA
                4          0.12                0.80                0.24
                6          0.18                1.20                0.36
                8          0.24                1.60                0.48
               10          0.30                2.00                0.60
               12          0.36                2.40                0.72
               12          0.36                2.40                0.72
               16          0.48                3.20                0.96
               18          0.54                3.60                1.08
               20          0.60                4.00                1.20
               24          0.72                4.80                1.44
             Pipe man-hours include handle, haul, place, and align in trench.


             2.8.2  Handle and install pipe and cast iron soil—No hub

             Facility—Industrial plant (underground drainage piping)

             Pipe size    Pipe set and align  Handle install fitting  Couplings
              Inches          MH/LF                MH/EA             MH/EA

                4              0.10                 0.24               0.40
                6              0.15                 0.36               0.60
                8              0.20                 0.48               0.80
               10              0.25                 0.60               1.00
               12              0.30                 0.72               1.20
               12              0.30                 0.72               1.20
               16              0.40                 0.96               1.60
               18              0.45                 1.08               1.80
               20              0.50                 1.20               2.00
               24              0.60                 1.44               2.40
             Pipe man-hours include handle, haul, place, and align in trench.