Page 9 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 9

xxiv Introduction


            Labor productivity and analysis
            Labor—Man-hour unit rates

            Labor productivity is concerned with direct craft labor. Direct craft labor means
            the craft is working in the field erection of process piping and equipment. The
            man-hour is defined as the amount of work performed by the average worker in
            one hour.
               Formula: Man-Hour¼Time Quantity (Refer to the Unit Quantity Method)
               Once time values are known for a construction task, they are multiplied by
            the quantity. Time may be for individuals or for crew work, and it is based on the
            construction task. Time is expressed relative to a unit of measure, such as LF,
            EA, SF, and Ton. The unit of time may be a minute, hour, day, month, or year.
               Examples of man-hour units are as follows:
            (1) HRSG—seal weld side, roof, and floor casing field seams; number of
                welder man-hours per lineal foot of field welding, 0.35MH/LF
                                                                 00
            (2) Welding butt weld, carbon steel, arc-uphill, WT<¼0.375 ; number of
                welder man-hours per diameter inch of welding, 0.50MH/DI
               The union/nonunion craft, experience factor, and PF&D allowances have
            been included in the craft unit man-hours. Standard unit rates can be used to
            estimate work anywhere in the United States. The estimator must determine
            all factors that will affect labor productivity and overtime impacts. The man-
            hour units and quantities are based on historical data that have been verified
            by statistical analysis, and the man-hour rates are competitive.


            Productivity measurement

            Historical records provided the direct craft man-hour data for field installation of
            piping and equipment. Two methods for the measurement of construction time
            were used to collect, analyze, and compile the actual man-hour data in this book.
            (1) Foreman report—job cost by cost code and type
            (2) Nonrepetitive one-cycle time study
            (3) There are several ways in which actual time data are compiled and ana-
                lyzed from the foreman’s report. One method is to compile data for
                man-hour analysis obtained from the foreman’s report for mathematical
                analysis. Then, the engineer will determine the productivity rates. The
                productivity rates are then entered into the estimating system to be used
                to estimate future work that is similar.

               The following example will enable the reader to set up cost codes and ana-
            lyze historical data, from field erection cost reports, using graphic analysis to
            verify direct craft man-hours.
   4   5   6   7   8   9   10   11   12   13   14