Page 10 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 10

Introduction xxv



             Analysis of Foreman’s Report
             Coal-Fired Power Plant
             Project: Boiler Erection-Field Welding Rates
             JOB COSTS BY COST CODE AND COST TYPE

                                                        HOURS
                                                        PER DIEM
             PHASE     DESCRIPTION                      Tube welding—MH per weld
             LABOR     BURDEN                           Design pressure (PSI)
                       Tube size (OD)                   1501–2000
             000000    Over 1 and including 1-1/2 heli arc  3.00
                                          00
                           00
                              00
                                          00
             000000    Over 1-1/2 and including 2 heli arc  3.70
             000000    Over 2 and including 2-1/2 heli arc  4.20
                                          00
                           00
                                          00
                              00
             000000    Over 2-1/2 and including 3 heli arc  4.80
                                          00
                           00
             000000    Over 3 and including 3-1/2 heli arc  5.30
                                          00
                              00
             000000    Over 3-1/2 and including 4 heli arc  5.90
                           00
             000000    Over 4 and including 4-1/2 heli arc  6.50
                                          00
                                             00
                              00
             000000    Over 4-1/2 and including 5-1/2 heli arc  7.70
             000000    Over 5-1/2 and including 6-1/2 heli arc  9.00
                                             00
                              00
             Foreman’s report
                Information for man-hour analysis is obtained from the foreman’s report.
             The foreman’s report is used to find the number of man-hours for a task.
             The report is used for cost and time control. The cost engineers and welding
             quality control in the field monitor and verify the work. These reports are col-
             lected for the field installed piping and equipment. From the reports and review
             of the specifications, codes, and drawings, the cost engineer and the estimator
             will examine the data for consistency, completeness, and accuracy. Reports are
             collected for similar work, and the data are entered into a spreadsheet. The
             spreadsheet prepares the data for mathematical analysis. The engineer and esti-
             mator determine the productivity rate. The rate is used for future cost analysis
             and estimating similar scopes of work.
             Validate and clarify man-hour table using graphic analysis
             The historical data collected in the field taken over time can be discrete or con-
             tinuous. The collected data are summarized into a tabular arrangement by inter-
             vals that compacts the data into viewable records called a histogram. Plotting of
             data using graphic techniques allows results to be displayed in pictorial form.
             This provides insight into a data set to help with testing assumptions, model
             selection, regression model validation, estimator selection, relationship identi-
             fication, factor effect determination, and outlier detection. Plotting of data
             allows the estimator to check assumptions in statistical models and communi-
             cate the results of an analysis.
   5   6   7   8   9   10   11   12   13   14   15