           1.5   A.   A project is expected to recover 200 million STB of oil. The project will
                    require installing an infrastructure (e.g., platforms, pipelines, etc.) that costs
                    $1.2 billion and another $0.8 billion in expenses (e.g., royalties, taxes, operating
                    costs). Breakeven occurs when revenue = expenses. Neglecting the time value
                    of money, what price of oil (in $/STB) is needed to achieve breakeven?
                 b.   Suppose a fire on the platform adds another $0.5 billion to project cost.
                    Neglecting the time value of money, what price of oil (in $/STB) is
                    needed to achieve breakeven?
           1.6   A.   The water cut of an oil well that produces 1000 STB oil per day is 25%.
                    What is the water production rate for the well? Express your answer in STB
                    water per day.
                 b.  What is the WOR?
           1.7   A.   Fluid production from a well passes through a separator at the rate of
                     1200 MSCF gas per day and 1000 STB oil per day. What is the separator
                     GOR in MSCF/STB?
                 b.   Based on this information, would you classify the fluid as black oil or
                    volatile oil?
           1.8   A.  How many acres are in 0.5 mi ?
                                            2
                 b.   If one gas well can drain 160 acres, how many gas wells are needed to
                    drain 1 mi ?
                            2
           1.9   A.   A wellbore has a total depth of 10 000 ft. If it is full of water with a pressure
                    gradient of 0.433 psia/ft, what is the pressure at the bottom of the wellbore?
                 b.   The pressure in a column of water is 1000 psia at a depth of 2300 ft. What
                    is the pressure at a shallower depth of 2200 ft.? Assume the pressure gra-
                    dient of water is 0.433 psia/ft. Express your answer in psia.
           1.10  A.   Primary recovery from an oil reservoir was 100 MMSTBO where 1
                     MMSTBO = 1 million STB of oil. A water flood was implemented
                     following primary recovery. Incremental recovery from the water flood
                     was 25% of original oil in place (OOIP). Total recovery (primary recovery
                     plus recovery from water flooding) was 50% of OOIP. How much oil (in
                     MMSTBO) was recovered by the water flood?
                 b.  What was the OOIP (in MMSTBO)?
           1.11  A.   A core contains 25% water saturation and 75% oil saturation before it is
                    flooded. Core floods show that the injection of water into the core leaves
                    a residual oil saturation of 25%. If the same core is resaturated with oil
                    and then flooded with carbon dioxide, the residual oil saturation is 10%.
                    What is the  displacement efficiency of the water flood? Assume displace-
                                                            )
                                                              S
                    ment efficiency can be estimated as E D  S (  oi  S / .
                                                               oi
                                                           or
                 b.  What is the displacement efficiency of the carbon dioxide flood?
           1.12  The revenue from gas produced by a well is $6 million per year. The gas drains an
                 area of 640 acres. Suppose you have 1 acre in the drainage area and are entitled to
                 25% of the revenue for your fraction of the drainage area, which is 1 acre/640
                 acres. How much revenue from the gas well is yours? Express your answer in $/yr.
   33   34   35   36   37   38   39   40   41   42   43