Page 173 - Machinery Component Maintenance
P. 173

Process Machinerx Piping   155

                      If leakage persists, piping support and flexibility must be examined.
                      It  may  be  necessary to revise the support system or  install spring
                      hangers to lower bending moments.
                      If  leakage occurs during rainstorms, it  will  be  necessary to  install
                      sheet metal rain shields, which may cover the top 180" of the flange,
                      to prevent such leakage. These should be located about four inches
                      away  from the flange surface and  should have  sufficient width to
                      cover the bolts plus two inches on each side.
                      If leakage occurs during sudden changes in process temperatures, ex-
                      amine the process sequence to determine if steps can be taken to min-
                      imize rapid heat-up or cooling of lines. It may only be necessary to
                      open a valve more slowly.



                            Recommendations for the Installation, Fabrication,
                            Testing and Cleaning of Air, Gas or Steam Piping*

                    The importance of starting any compressor with clean piping, particu-
                  larly on the intake to any cylinder, cannot be over-emphasized. This is
                  particularly important with multi-stage high-pressure compressors where
                  special metallic packing is required and parts are much more expensive
                  than in a low-pressure compressor. Any dirt, rust, welding beads or scale
                  carried into the compressor will cause scored packing rings, piston rods,
                  cylinder bores, and pitted, leaky valves.
                    It is important that the piping be fabricated with sufficient flange joints
                  so that it can be dismantled easily for cleaning and testing. It is far better
                  to clean and test piping in sections before actual erection than after it is in
                  place.
                    If it is necessary to conduct the final test when the piping is in position,
                  care should be taken to provide vents at the high spots so that air or gas
                  will not be trapped in the piping. Make provision for complete drainage
                  after the test  is completed. These connections should be planned in  ad-
                  vance.
                    When piping is cleaned in sections before erection, it is possible to do a
                  thorough job of  eliminating all acid. This is difficult to do with piping
                  erected and in position, because carry-over of  acid into the cylinders is
                  almost certain to occur when the machine is started. This can cause ex-
                  tensive damage.
                    The use of chill-rings for butt welds in piping is recommended. This
                  prevents welding beads from getting into the pipe to carry through, not
                  only on  the original starting, but later on during operation.

                    Rcfcr to appendices at the end of this chapter for typical  checklists.
   168   169   170   171   172   173   174   175   176   177   178