Page 81 - Mathematical Models and Algorithms for Power System Optimization
P. 81

Optimization of Annual Generator Maintenance Scheduling 71

               3.6.3 Description of the Input Data

               The input data of generator maintenance scheduling mainly consists of the following eight
               parts: GMS calculation begin card (BEGIN card), generator maintenance information card (GE
               card), area maintenance capacity restraint card (RA card), maintenance time nonoverlapping
               card (RP card, for power plants), maintenance time nonoverlapping card (RG card, for
               generator groups), equivalent load curve card (CC card), GMS data file end card (END card),
               and information comment card (** card).

               Among them, BEGIN, GE, CC, and END cards are necessary in the input data files; otherwise
               the procedure cannot be executed. Although the RA, RP, and RG cards can be combined by the
               procedure, users can at-will construct the ES knowledge base for the system based on the
               characteristics of their own system. Therefore, the GMS solution process can be intervened to
               obtain the generator maintenance scheduling in compliance with the system requirements.
               The details of the eight data cards are described as follows:
               (1) GMS calculation begin card (BEGIN card), which includes scheduling start time, end
                    time, as well as the case name and print options (see Table 3.3).


                                          Table 3.3 Contents of BEGIN card
                          Identifier                         Contents

                          BEGIN                      BEGIN, denoting the begin card
                          START                Schedule start time (YY-MM-DD), for example,
                                                             94-12-31
                          CASENAME                      Case name (optional)
                          P                     Print options, P¼0: output the calculation
                                                            results only
                                          P¼1: output the reduced input data and calculation results

               (2) The generator maintenance information card (GE card), which includes all information
                    required for maintenance scheduling of generating units (see Table 3.4).


                                           Table 3.4 Contents of GE card
                          Identifier                         Contents

                          GE               GE, denoting the generator maintenance information card
                          AERA                Name of area where the generating unit is located
                          PLANT              Name of power plant where the generator is located
                          GEN                          Name of generating unit
                          BUREAU          Fill in B, which means the generator belongs to the Bureau,
                                                         otherwise left blank
                          CAP             Rated capacity of the generator (MW, if CAP¼0 or left blank,
                                                    it means this line is header boiler)
                                                                                  Continued
   76   77   78   79   80   81   82   83   84   85   86