Page 83 - Mathematical Models and Algorithms for Power System Optimization
P. 83

Optimization of Annual Generator Maintenance Scheduling 73

                                           Table 3.6 Contents of RP card
                          Identifier                         Contents

                          RP              RP, denoting the maintenance time nonoverlapping (power
                                                            plant) card
                          PLANT1                        Name of power plant 1
                          PLANT2          Name of power plant 2 (may be the same as power plant 1)
                          DT               Time interval (days) between maintenance time, optional
                          PCAP            Lower limit of unit capacity that this card works, if left blank,
                                                            no such limit
                          P-START         Start date (YY-MM-DD) of maintenance time nonoverlapping
                                                          restraint, optional
                          P-END           End date (YY-MM-DD) of maintenance time nonoverlapping
                                                          restraint, optional
                         Notes: (1) If PLANT1¼PLANT2, it means the maintenance time of generating unit in the same
                         power plant cannot be overlapped; if PLANT16¼PLANT2, it means the maintenance time of units
                         in the two power plants cannot be overlapped. (2) If P-START and P-END are left blank, it means
                         that the maintenance time nonoverlapping (for power plants) card will work in the entire GMS
                         study period.


               (5) Maintenance time nonoverlapping (generator) card (RG) can restrain two given units from
                    overlapping in their maintenance time, with card contents shown in Table 3.7.



                                           Table 3.7 Contents of RG card
                          Identifier                         Contents

                          RG                 RG, denoting the maintenance time nonoverlapping
                                                      (generator) card in this line
                          GEN1                           Name of generator 1
                          GEN2                           Name of generator 2
                          DT               Time interval (days) between maintenance time, optional
                          G-START         Start date (YY-MM-DD) of maintenance time nonoverlapping
                                                          restraint, optional
                          G-END           End date (YY-MM-DD) of maintenance time nonoverlapping
                                                          restraint, optional
                         Note: If G-START and G-END are left blank, it means that the maintenance time nonoverlapping
                         (generator) card will work in the entire GMS study period.


               (6) Equivalent load curve card (CC). The equivalent load of the system in each period is
                    composed of actual forecast load minus the output of hydro plants and small unit and the
                    power provided by the external system in the stress reduction period, plus the disabled
                    capacity (capacity of units not reaching their full capacity) of the system during
                    such period.
                    The contents of equivalent load curve card are shown in Table 3.8.