Page 87 - Mathematical Models and Algorithms for Power System Optimization
P. 87
Optimization of Annual Generator Maintenance Scheduling 77
Expert rules for area constraints are shown in Table 3.13.
Table 3.13 Expert rules for area constraints
Max. Maintenance
ID Area Name Capacity (MW) Start Time End Time
RA HD 250.0 1994-05-01 1994-12-31
Some expert rules for power plant constraints are shown in Table 3.14.
Table 3.14 Some expert rules for power plant constraints
Name of Name of Maintenance
ID Plant i Plant j Interval RPC Start Time Start Time
RP MATOU1 MATOU1 5
RP MATOU2 MATOU2 5
RP SHEXIAN SHEXIAN
RP MATOU2 XING2 1994-03-15 1994-05-31
Some expert rules for unit constraints are shown in Table 3.15.
Table 3.15 Some expert rules for unit constraints
Maintenance
ID Name of Unit i Name of Unit i Interval Start Time Start Time
RG SA1 SA2 20 1994-01-01 1994-12-31
3.7.2 Part of Output Results
Due to limited space, this section only provides a partial example of the outputs, including
maintenance start/end time and durations for some units, as shown in Fig. 3.11 and Table 3.16.
Table 3.16 gives the GMS results of this real system, in which only the part concerning
generators is given in detail.