Page 88 - Mathematical Models and Algorithms for Power System Optimization
P. 88

78   Chapter 3




































                                                  Fig. 3.11
                 Outputs of maintenance start and end time and durations of some units. Maintainable
                               capacity¼Total capacity total load in each interval.






                        Table 3.16 Some detailed results of generator maintenance schedule
                                                       Maintenance   Maintenance
             Plant           Generator   Capacity (MW)  Start Time    End Time      Duration
             BAOJ              BD4J          50.0       1994-01-06    1994-02-09       35
             BAOJ              BD2J          25.0       1994-02-17    1994-02-24       8
             BAOJ              BD6J          25.0       1994-03-01    1994-03-08       8
             BAOJ              BD1J          25.0       1994-03-14    1994-03-21       8
             BAOJ              BD7J          50.0       1994-04-19    1994-04-28       10
             BAOJ              BD3J          50.0       1994-05-13    1994-05-21       9
             BAOJ              BD5J          50.0       1994-05-26    1994-06-03       9
             BAOJ              BD1J          25.0       1994-08-05    1994-08-12       8
             BAOJ              BD6J          25.0       1994-08-21    1994-08-28       8
             BAOJ              BD4J          50.0       1994-09-02    1994-09-11       10
             HANJ              HD1J           12        1994-01-12    1994-01-16       5