Page 88 - Mathematical Models and Algorithms for Power System Optimization
P. 88
78 Chapter 3
Fig. 3.11
Outputs of maintenance start and end time and durations of some units. Maintainable
capacity¼Total capacity total load in each interval.
Table 3.16 Some detailed results of generator maintenance schedule
Maintenance Maintenance
Plant Generator Capacity (MW) Start Time End Time Duration
BAOJ BD4J 50.0 1994-01-06 1994-02-09 35
BAOJ BD2J 25.0 1994-02-17 1994-02-24 8
BAOJ BD6J 25.0 1994-03-01 1994-03-08 8
BAOJ BD1J 25.0 1994-03-14 1994-03-21 8
BAOJ BD7J 50.0 1994-04-19 1994-04-28 10
BAOJ BD3J 50.0 1994-05-13 1994-05-21 9
BAOJ BD5J 50.0 1994-05-26 1994-06-03 9
BAOJ BD1J 25.0 1994-08-05 1994-08-12 8
BAOJ BD6J 25.0 1994-08-21 1994-08-28 8
BAOJ BD4J 50.0 1994-09-02 1994-09-11 10
HANJ HD1J 12 1994-01-12 1994-01-16 5