Page 69 - Oil and Gas Production Handbook An Introduction to Oil and Gas Production
P. 69

Most processes use a mixed refrigerant (MR) design. The reason is that the
          gas has  a heat load to temperature (Q/T)   curve that must be closely
          matched to improve stability and efficiency, see the figure below. The curve
          tends to show three distinct regions, matching the pre-cooling, liquefaction
          and sub-coiling stages. The refrigerant gas composition will vary based on
          the individual design, as  will the power requirement of each stage, and is
          often a patented, location-specific  combination of one or two main
          components and several smaller,  together with careful  selection  of  the
          compressed  pressure and expanded  pressure of the refrigerant, to match
          the LNG gas stream.

          Typical LNG train power use is about 28 MW per million tons of LNG per
          annum  (mtpa), corresponding to typically 200 MW for the largest  trains of
          7.2 mtpa, or 65 MW per stage. In addition other consumers in gas treatment
          and pre-compression add to total energy consumption and bring it to some
          35-40 MW per mtpa.

          For each train, the cooling medium is first passed though  its cooling
          compressor. Since Pressure times Volume over Temperature  (PV/T)
          remains constant, it results in a significant temperature rise which has to be
          dissipated, typically in a  seawater heat  exchanger as shown  in the  figure
          above (as indicated by the blue wavy line). It then goes though one or more
          heat exchangers/cold boxes, before it expands either  though  a valve  or a
          turbo-expander causing the temperature to drop significantly. It is then
          returned to cool its cold box before going on to the compressor.

          The pre-cooling stage cools the gas to a temperature of about -30 to -50ºC
          in the precooling cold box. The cooling element is generally propane or a
          mixture of propane and ethane and small quantities of other gases. The pre-
          cooling cold box also cools the cooling medium for the liquefaction and sub
          cooling stage.

          The  liquefaction  process takes the gas down from -30ºC to about -100-
          125ºC typically based on a mixture of methane and ethane and other gases.
          It cools the LNG stream as well as the refrigerant for the final stage.

          Sub-cooling serves to bring the gas to final stable LNG  state  at around
          162ºC. The refrigerant is usually methane and/or nitrogen.

          5.2.2 Storage, transport and regasification
          Storage at the terminals and on LNG carriers is done in cryogenic tanks at
          atmospheric pressure  or slightly  above, up to 125 kPa. The  tanks are
          insulated, but will not keep LNG  cold  enough to avoid evaporation. Heat

                                           67
   64   65   66   67   68   69   70   71   72   73   74