Page 146 - Orlicky's Material Requirements Planning
P. 146

CHAPTER 7   Processing Logic                                                    125


             Be aware that when safety stock is planned through the MPS, it has the added
        impact of planning additional components in matched sets, allowing the safety-stock
        quantities of end items actually to be built. This will increase overall inventory invest-
        ment. The preceding arguments regarding the proper place of safety stock can be
        summed up by stating that safety stock is applied properly only to inventory items sub-
        ject to independent demand when the actively synchronized replenishment (ASR) lead
        time is greater than the customer tolerance time. The resupply (completion) of manufac-
        tured items need not be erratic because performance to schedule is controllable, particu-
        larly in an MRP environment. Establishment of a replenishment buffer for component
        items can compress the recovery time dramatically when volatility is experienced. This is
        covered in Part 4.


        COVERAGE OF NET REQUIREMENTS
        The quantities and timing of net requirements for a given inventory item can be thought
        of as indicating impending shortages caused by lack of cov erage. Assuming an adequate
        planning horizon, an MRP system detects such shortages sufficiently in advance to allow
        their coverage to be planned in an orderly manner. An MRP system detects future poten-
        tial shortages and plans their coverage so that actual shortages will not occur.



                                       Planned Orders
        In an MRP system, net requirements are covered by planned orders, that is, new orders for
        the respective items scheduled for release in the future. Depending on the planning hori-
        zon, the level of the item in the product structure, and the applicable lot-sizing rule, an
        item with net requirements will have one or more planned orders indicated. The timing
        of the first (earliest) planned order is governed by the timing of the first net requirement.
        The order quantity must equal or exceed the net requirement. If this quantity exceeds the
        net requirement, the timing of the next (second) planned order may be affected.  A
        planned order may cover net requirements occurring in one or more planning periods.
             To generate a planned order correctly, the system must determine the following:
             1. The timing of required order completion (due date)
             2. The timing of order release
             3. The order quantity

             The timing of order completion derives, of course, from the timing of the net
        requirement being covered. As mentioned previously, the timing of the planned-order
        release is arrived at by offsetting for lead time, that is, by subtracting the value of the lead
        time (expressed in shop calendar units) from the shop calendar date of order completion.
             The individual-item lead times used by the MRP system in deter mining planned-
        order releases are, by necessity, estimates in most cases. The lead-time value of the four
        periods used in the preceding example represents the amount of time that could be
   141   142   143   144   145   146   147   148   149   150   151