Page 149 - Orlicky's Material Requirements Planning
P. 149

128                                                                 PART 2   Concepts


        since the late 1950s when the first MRP systems were implemented. Because there are so
        many different lot-sizing techniques to be described, an entire chapter (Chapter 8) will be
        devoted to the subject.


        EXPLOSION OF REQUIREMENTS
        The key to the entire MRP (replanning) process is the linkage between parent and com-
        ponent-item records. There is only one logical link between items on contiguous levels of
        the product structure, and that is the parent planned-order release and the component
        gross re quirement. These coincide in time because the component item(s) must be
        planned to be available at the time the parent order is released for produc tion, at which
        time the component item(s) will be consumed. The linkage of parent and component
        inventory records is shown in Figure 7-9.
             The MRP process, that is, the so-called explosion of requirements from the MPS
        down into the various component-material levels, is guided by the logical linkage of
        inventory records. Gross requirements for the high-level items are processed against
        inventory (on hand and on order in each time period) to determine net requirements,
        which then are covered by planned orders. The quantity and timing of planned-order
        releases determine, in turn, the quantity and timing of component gross requirements.
        This procedure is carried out repetitively for items on suc cessively lower levels until a
        purchased item is reached, at which point the explosion progression terminates. The
        MRP process stops when all the explosion paths that follow the branches of the BOM
        have reached purchased items (component parts or raw materials). The results of a
        requirements explosion for three items on contiguous levels are illustrated in Figure 7-10.

           FIGURE 7-9
                                                           Period
           Linkage of parent
           and component        Parent              1   2  3   4   5  6
           records.





                                Planned-order releases  20        25



                                Component
                                Gross requirements     20         25
   144   145   146   147   148   149   150   151   152   153   154