Page 153 - Orlicky's Material Requirements Planning
P. 153

132                                                                 PART 2   Concepts


           FIGURE 7-12
                                                 Period
                                 End
           Master                Item
           production                    1    2    3     4    5
           schedule.
                                  A     100       100        100
                                  B     15   20    25   20    15

                                  C     50    60        60


           FIGURE 7-13
                                                            Period
           MPS interface:       Item A
           gross                Lead time: 1          1   2   3  4   5
           requirements.
                                Gross Requirements   100    100     100
                                Schedule Receipts    100
                                On Hand           80  80 80 –20 –20–120
                                Planned-Order Releases   20     100



                                                         20     100


        in the first five periods. Under this option, the MPS does not reflect a production plan but
        a requirements plan. This is not a recommended treatment—confusion will arise if man-
        agement views the schedule as a plan of production, but the MRP system does not treat
        it that way.
             The second alternative treats the MPS as reflecting production requirements; that is,
        300 units of item A are to be finished in the first five periods. In this case, the system must
        be programmed to exclude any on-hand quantities (but not on-order quantities) from the
        netting pro cess for highest-level items. This requires a modification of the regular pro-
        cessing logic, applicable to these items only. This procedure is sound, and it presupposes
        that end-item demand has been netted against on-hand inven tories during the prepara-
        tion of the MPS. An exam ple of this alternative is shown in Figure 7-14.
             Under each of the two alternative treatments just discussed, the MPS, in conjunction
        with the MRP system, will “produce” item A in the quantities indicated—the system will
        order correct quantities to be assembled or completed, and barring some difficulty, item
        A will be available according to what the schedule calls for.
             The third option treats the MPS as a schedule of planned-order releases, which
        means that the schedule will not “produce” the end items but only their components
        (Figure 7-15). The assembly of end items then would have to be ordered apart from the
        MRP system, most likely via a final assembly schedule. This may or may not be desirable
        depending on the type of product being manufactured. If the end items in the MPS are
   148   149   150   151   152   153   154   155   156   157   158