Page 150 - Orlicky's Material Requirements Planning
P. 150

CHAPTER 7   Processing Logic                                                    129


           FIGURE 7-10
                                                                  Period
           Explosion of
           requirements.       Item A – Level 1       1   2   3  4   5   6  7   8  9
                                Gross Requirements    10     15  10 20   5     10  15
                                Scheduled Receipts           14
                                On Hand           12  2   2   1  –9 –29 –34 –34 –44 –59
                                Planned-Order Releases    9  20  5      10  15


                               Item B – Level 2

                                Gross Requirements        9  20  5      10 15
                                Scheduled Receipts
                                On Hand           28 28 19 –1    –6 –6 –16 –31 –31 –31
                                Planned-Order Releases  1  5     10  15


                               Item C – Level 3
                                Gross Requirements    1   5      10 15
                                Scheduled Receipts
                                On Hand            8  7   2   2  –8 –23 –23 –23 –23 –23
                                Planned-Order Releases    8  15



             In this example, component items B and C do not have multiple parents; that is, they
        are not common-usage items. In the real situation, however, multi ple parents can be
        expected to exist, particularly for low-level items. If the explosion progressed in the man-
        ner shown in Figure 7-10, that is, straight down from item A to its immediate components
        and from those to their compo nents, the results would have to be recomputed as subse-
        quent explosions of high-level items revealed common usage of items B and C (and other
        com ponents of A). While the final result would be the same, the data-processing efficien-
        cy would be unnecessarily low.
             The downward progression from one product level to another just described is
        called an explosion. Net requirements are developed by applying quantities of each item
        on hand and on order to meet gross requirements for the item at each level. This netting
        process may seem laborious, but it cannot be circumvented or shortcut; net requirements
        on the parent level must be determined before the correct gross and net requirements on
        the component level can be determined.
             To cover net requirements, the MRP program develops a time-phased schedule of
        planned orders for each item, including orders, if any, to be released immediately plus
        orders scheduled for release in specified future periods. Planned-order schedules will be
   145   146   147   148   149   150   151   152   153   154   155