The Zeepipe challenge
prior to commencement of the precommissioning and commissioning opera-
tions.
CONCLUDING REMARKS
By adopting the long-distance pigging concept, both the precommissioning
and commissioning operations have been significantly simplified. The need
for a midline platform on the Sleipner to Zeebrugge pipeline has been
eliminated, and more cost-effective alternatives are introduced for the future
compressor platform tie-in. This has further reduced the maintenance re-
quirement, and also eliminated intermediate pig handling during the opera-
tional phase.
ACKNOWLEDGEMENT
Zeepipe is organized as a joint venture with the following ownership
configuration:
Company Ownership (%)
Den norske stats oljeselskap A/S(Statoil) 70'
Norsk Hydro produksjon A/S 8
A/S Norske Shell 7
Esso Norge A/S 6
Elf Aquitaine Norge A/S 3.2985
Saga Petroleum A/S 3
Norsk Conoco A/S 1.7015
Total Marine Norsk A/S 1
"Including direct Norwegian state economic participation of 55%.
Statoil is the operator of the Zeepipe joint venture.