Page 209 - Pipeline Pigging Technology
P. 209

Pipeline  Pigging  Technology


     internal inspection  of the pipeline  to verify  its mechanical  integrity.

        BACKGROUND


        The following were  the primary reasons for the  inspection:

           Public safety  - a  need  for  AGEC  to  determine  the  line's mechanical
              integrity given its concern  for public  safety.

           Pipeline  coating concerns - the  pipeline is coated with  double-wrap
              polyethylene tape which is prone  to disbondment. Disbondment is
              difficult to detect, and corrosion under the disbonded coating is only
              detectable  with an internal inspection  tool.

           Polymer formation  - during the life of the pipeline, maximum through-
              put  had  decreased  by  26%. This  decreased  capacity  seriously af-
              fected AGEC's product transfer capability such that it would force a
              reduction in ethylene plant production under certain circumstances.
              In order to perform an internal inspection, the pipeline polymer had
              to be  removed.

        Project   considerations


        Because of the uncertainties associated with the internal polymer,  coupled
     with the requirement to evacuate the line to install additional pigging stations,
     the  actual  cleaning and  inspection  was  to  take  place  coincident  with  an
     ethylene  plant  maintenance  shutdown.  The  pipeline  was  completely
     decommissioned,   with  all pigging  taking place  in  nitrogen.  This not  only
     eliminated the risks associated with sticking a pig in ethylene service, but also
     eliminated  the  prospect  of  inadvertently  interrupting  ethylene  supply  to
     customers. The length of the project was set at 28 days, the time planned for
     the ethylene plant  turn-around.



        PROJECT ORGANIZATION



        To provide pigging experience, Novacorp was hired to engineer, procure
     and construct  the capital works and to clean and inspect the pipeline. AGEC


                                       190
   204   205   206   207   208   209   210   211   212   213   214