Page 212 - Pipeline Pigging Technology
P. 212

Ethylene pipeline  cleaning


     interface  length  of  contaminated  ethylene.  To  expedite  the  process,
     decommissioning   was  done  in  three  stages with  three  nitrogen  injection
     points  (see  Fig.l). Nitrogen injection would begin at the  south  end of the
     pipeline; as the interface passed the next injection site, the previous section
     was shut in, depressured,  and prepared for capital work. Due to the amount
     of  nitrogen  involved  in  decommissioning,  it  was  necessary  to  use  three
     nitrogen service companies, each with one injection  point.

        Capital   works


        In order to clean and inspect the entire  180-km line in a 28-day period,  the
     pipeline had to be separated into four sections. The section lengths were set
     at 75km, 51km, 35km, and  19km, based primarily on the amount of polymer
     expected in each section. The deposition problem was considered to be more
      severe at the north end of the line, which is furthest from the plants, than at
      the south end, so the section lengths decreased proportionally. Each section
     had  its own  launch and  receive  traps,  as well as facilities  to  separate  the
     polymer from the nitrogen. Four simultaneous pigging operations proceeded
     on a 24-hour-a-day basis.
        For capital works, Novacorp was retained to design, procure, fabricate and
     install all additional pig trap sites complete with polymer-separation systems.
     The  receive  sites  had  separation  facilities  to  remove  any debris  from  the
     nitrogen  stream as it was vented  to  the  atmosphere.  These  consisted  of a
     separator/knock-out drum, pressure  let-down valve and final filtration bags
     (see  Fig.2).

        Cleaning and inspection

        Cleaning commenced immediately upon completion of the capital works
     for  a section. All cleaning and inspection  tools were  propelled  by nitrogen,
     with  their  speed  governed  by  a  control  valve  at  the  receive  sites.  The
     proposed  schedule  of cleaning and  inspection  runs is shown  in Fig.3; this
      selection  of pigs was designed to progressively remove the polymer debris
     from the pipe wall and successfully carry it out to the separator and filter bags.
        The  cleaning  programme  assumed  the  majority  of  polymer  would  be
     removed   during  the  1400-kPa  (200-psO  runs  when  the  separator  was  in
      service. The separator would then be by-passed for all inspection  runs,when
     pressures were 3500kPa  (500psf).
        The four  sections were  totally independent  for cleaning. Each had dedi-
      cated resources  with operations  proceeding 24 hours a day.


                                       193
   207   208   209   210   211   212   213   214   215   216   217