Page 215 - Pipeline Pigging Technology
P. 215
Pipeline Pigging Technology
Fig.4. Interface log.
prior, visits were made to the landowners within a one-mile radius of a work
site to highlight any work activities which affected the area, and to answer any
questions and concerns they had.
PROJECT EXECUTION
Decommissioning
Decommissioning commenced at 12.00 noon on Sunday 13th May, 1990.
3
A nitrogen injection rate of 510sm /hr was selected, based on a theoretical
calculation to maintain an interface velocity of 1.1 m/s for fully-turbulent flow.
Target nitrogen injection rates were initially restricted by a high pressure
drop through a 2-in injection valve on the pipeline. Injection then stopped to
connect to a second injection point. After approximately one hour, nitrogen
3
injection recommenced, and rates of 510sm /hr were achieved. Fig.4 shows
the actual times for the interface to reach each block valve site, and the
corresponding length of the interface as measured.
The nitrogen front reached the north end of the pipeline (BV10) in 453hrs,
with an interface length of 1.7km. The contaminated ethylene was flared
using a combination of portable flares and a permanent flare.
Ethylene was successfully purged from the three southern sections. A
second, low-pressure, sweep of nitrogen was required on the north end when
ethylene was detected prior to cutting into the line. It is believed this ethylene
vapour was released from the polymer build-up in this section following a rest
196