Page 215 - Pipeline Pigging Technology
P. 215

Pipeline  Pigging  Technology




















                               Fig.4. Interface  log.

      prior, visits were made to the landowners within a one-mile radius of a work
      site to highlight any work activities which affected the area, and to answer any
      questions and concerns  they had.



        PROJECT        EXECUTION



        Decommissioning


        Decommissioning commenced at    12.00 noon on Sunday 13th May,  1990.
                                      3
     A nitrogen injection rate of 510sm /hr was selected,  based  on a  theoretical
      calculation to maintain an interface velocity of 1.1 m/s for fully-turbulent flow.
     Target  nitrogen  injection rates were  initially  restricted  by a high  pressure
     drop through a 2-in injection valve on the pipeline. Injection then stopped  to
      connect to a second injection point. After approximately one hour, nitrogen
                                               3
      injection recommenced, and rates of 510sm /hr were achieved. Fig.4 shows
      the  actual times for  the  interface to  reach  each  block  valve  site,  and  the
     corresponding  length of the  interface as measured.
        The nitrogen front reached the north end of the pipeline (BV10) in 453hrs,
     with  an  interface length  of  1.7km. The  contaminated ethylene  was  flared
     using a combination of portable flares and a permanent flare.
        Ethylene  was  successfully purged  from  the  three  southern  sections.  A
     second, low-pressure, sweep of nitrogen was required on the north end when
     ethylene was detected prior to cutting into the line. It is believed this ethylene
      vapour was released from the polymer build-up in this section following a rest


                                       196
   210   211   212   213   214   215   216   217   218   219   220