Page 74 - Pipeline Pigging Technology
P. 74

Pre-inspectton-survey activities












         PRE-INSPECTION-SURVEY ACTIVITIES
      FOR      MAGNETIC-FLUX INTELLIGENT PIGS






         INTRODUCTION



         The  determination  of  the  accessibility  of a pipeline  prior  to  intelligent
      inspection, and deciding on the level of preparation that will be required, are
      sometimes subject to differences of opinion between pipeline operators and
      inspection  contractors.  This may ultimately result in a failure to achieve  the
      specified  inspection results.
         The pipeline operator  expects  the inspection  survey pig to report  pipe-
      wall anomalies (internal and external) as small as  12mm diameter and only
      3mm deep. These are to be found and sized in, for example, a 30-iti diameter,
      100-km  long pipeline, which  has  a pipe-wall surface  of 478,536sq  m. It  is
      obvious that the pipe wall should be accessible and the running conditions
      should be optimized in order  to achieve the desired  inspection  result.
         Just  for  comparison,  a  30-in  intelligent pig  travelling at  3m/s  produces
      approximately 150,000 measurements per  second, and passes over a 12-mm
      anomaly in 0.004sec. In this available time, the sensors must record measure-
      ments  to determine  and  confirm  the  metal loss and  decide  on  internal or
      external location.
         This paper describes the possible causes for misunderstanding by detailing
      all the activities required prior to a pre-inspection survey. The fact that a single
      cleaning pig run does not produce  conclusive information on the pipe-wall
      surface condition may give rise to misunderstanding. Hence, this subject and
      many others  are detailed  below.
         Pipeline  surveys are  carried  out  as part  of an  overall maintenance pro-
      gramme;  the  inspection  contractor  should  therefore  have  access  to  all
      relevant pipeline data in order to be able to present  the survey report in the
      format that fits the maintenance programme.


                                        55
   69   70   71   72   73   74   75   76   77   78   79