Page 146 - Pipeline Risk Management Manual Ideas, Techniques, and Resources
P. 146

Design 6/123
               last.” The important thing is that the equipment fails in a mode   Example 6.3: Scoringsafety systems (Case C)
               that leaves the system in the least vulnerable condition.
                Three  examples  follow  of  the  application  of  this  point   In this example, a supplier delivers product via a high-pres-
               schedule.                                  sure pump into a pipeline section that relies on a downstream
                                                          section’s reliefvalve to prevent overpressure. The supplier has a
                                                          pressure switch at the pump site to stop the pump in the event of
               Example 6.1 : Scoring safety systems (Case A)   high pressure. The pipeline  owner inspects the pump  station
                                                          owner’s  calibration  and  inspection  records  for  this  pressure
                In the pipeline  section  considered here,  a pump  station is
               present. The pump is capable of overpressuring the pipeline. To   switch. The pump station owner remotely monitors the pump
               prevent this, safety devices are installed. A pressure-sensitive   station operation 24 hours per day.
               switch will stop the pump and allow product to flow around   Conditions present   Points
               the  station  in  a  safe  manner.  Should  the  pressure  switch
               fail to  stop the pump,  a relief  valve will  open  and  vent the   B   3
               entire pumped product stream to a flare in a safe manner. This   F-G   - 2.5
               station is remotely monitored by the transmission of appropri-   Total points = 0.5
               ate data (including pressures) to a control room that is manned
               24 hours  per  day. Remote  shutdown of the pump  from  this   Note that in this case credit is not given for a relief valve not
               control room is possible. Communications  are deemed to be   in the section being evaluated. The evaluator has decided that
               98% reliable.                              the downstream relief  valve does  not adequately protect the
                                                          pipeline section being assessed.
                     ~   ~   ~~~~~
               Condition\ present   Pornrr                 Note also that no points are given for the supplier’s remote
                                                          monitoring. Again, the evaluator has made the decision to sim-
               C                   6                      plify-he   does  not  wish  to be evaluating suppliers’ systems
               E                   3
               Total points = 9                           beyond the presence of direct overpressure shutdown devices
                                                          located at the site. Finally, note that the evaluator has awarded
                Note that two levels of safety are present (pressure switch   points  for  the  pipeline  owner’s  inspection  of  the  suppliers’
               and relief valve). and that full credit is given to the remote capa-   maintenance records. He feels that. in this case. an amount of
               bilities only after communication effectiveness is assessed   risk reduction is achieved by such inspections.

               Example 6.2: Scoring safety sjstems (Case B)   A4.  Material selection (62 pts)
                For this example, a section of a gas transmission pipeline has   The evaluator should look for evidence that proper materials
               a supplier  interconnect. This interconnect  leads directly to a   were  identified and  specified with  due  consideration  to  all
               producing gas well that can produce pressures and flow rates   stresses reasonably expected. This may appear to be an obvious
               which can overpressure the transmission pipeline. Several lev-   point, but when coupled with ensuring that the proper material
               els of safety are present at the well site and under the control of   is actually installed in the system, a number of historical fail-
               the producer. The producer  has agreed by contract to ensure   ures could have been prevented by closer consideration of this
               that the transmission pipeline owner is protected from any dam-   variable. The evaluator should find design documents that con-
               aging pressures due to the well operation. The pipeline owner   sider all anticipated stresses in the pipeline components. This
               monitors flow rates from the producer as well as pressures on   would include concrete  coatings,  internal and external  coat-
               the pipeline.  This monitoring  is on  a  24-hour  basis,  but  no   ings, nuts and bolts, all connecting systems. supports, and the
               remote control is possible.                structural (load-bearing) members of the system. Documents
                                                          should show that the corrosion potential, including incompati-
                                                          ble material problems and welding-related problems, was con-
               Conditionspresen I   Points
                                                          sidered in the design.
                                                           Most  importantly,  a  set  of  control  documents  should
               C                 6
               E                 1                        exist. These control documents, normally in the form of pipeline
               G                 -3                       specifications, give highly detailed data on all system compo-
               Total points = 4                           nents, from the nuts and bolts to the most complex instrumenta-
                                                          tion. The specifications will address component sizes, material
                Note  that credit  is given for condition  C even though the   compositions, paints and other protective coatings. and any spe-
               pipeline owner has no safety devices of his own in this section.   cial installation requirements. Design drawings specify the loca-
               The fact that the devices are present warrants points; the fact   tion and assembly parameters of each component.
               that they are not  under the  owner’s control  negates some of   When any changes to the pipeline are contemplated the control
               those points (condition G). Also, while contractual agreements   documents should be consulted. All new and replacement materi-
               may be useful in determining liabilities ufier an accident, they   als should conform to the original specifications  or the specifica-
               are not thought to have much impact on the risk picture. If the   tions must be formally reviewed and revised to allow different
               owner takes an active role in ensuring that the safety devices are   materials. By rigidly  adhering to these documents, the chance
               properly maintained, condition F would replace G. yielding a   of  mistakenly  installing  incompatible  materials  is  reduced.
               total point score of 5.                    A management-of-change (MOC) process should be in place.
   141   142   143   144   145   146   147   148   149   150   151