Page 148 - Pipeline Rules of Thumb Handbook
P. 148

Hydrostatic Testing  135

           86.6psig (200 feet ¥ 0.433 = 86.6psig). A test pressure equal
           to 90% of SMYS is 1,404psig. Since the test site is lower
           than the high end of the line, the 86.6psig is added to
           1,404psig to obtain a test site pressure of 1,491psig. The pres-
           sure at the end of the line will be 1,404psig which equates to
           90% of SMYS. The pressure at the low point equates to 96%
           of SMYS.
             Now, let’s assume a line has a high point elevation of 1,100
           feet, a low elevation point of 1,000 feet, and the elevation
           at the test site is 1,050 feet. The test pressure at the high
           point will need to be 1,404psig in order to meet the
           90% of SMYS requirement. The pressure at the low point
           will be 1,447psig, and the pressure at the test site will be
           1,426psig.                                            Figure 2. Typical  pressure  manifold.  Courtesy  Milbar
             When testing offshore lines, the pressure at or below the  Hydrotest.
           water surface will be the same as at the low elevation point
           due to the offsetting external sub-sea pressure head. If the
           line previously described was laid offshore, the test pressure
           at the water surface would be 1,404psig. The elevations are
           as follows:

             Top if riser      +11 feet
             Test site          +7 feet
             Water surface       0 feet
             Pipe depth       -168 feet

           The test pressure at the test site would be 1,404 - (7 ¥ 0.445)
           or 1,401psig. At the top of the riser, the test pressure would
           be 1,404 - (11 ¥ 0.445) or 1,399psig.
             The typical profile shown in Figure 1 represents a pipeline
           that requires testing. The pipeline crosses a river at approxi-
           mately MP 5 and river water will be used to test the line. Test
                                                                  Figure 3. Typical test manifold. Courtesy Milbar Hydrotest.
           sections 1 through 5 have been chosen as indicated. The
           lengths of sections 3 and 4 are limited by elevation difference.
           This line was designed to operate at 936psig or 72% of the
           SMYS of 30≤¥ 0.375≤wt API 5LX X52 pipe for Class I loca-
           tions, and 60% of the SMYS of 30≤¥ 0.390≤wt API 5LX X60
           pipe for Class II locations, and 50% of the SMYS of 30≤¥
           0.438≤wt API 5LX X65 for Class III locations.
             The pipeline crosses one railroad, one highway, and the
           river. It also includes one main line block valve assembly.
           The valve assembly, river crossing, and road crossing were
           pre-tested before installation and are tested again after
           installation.
             Four test manifolds were installed to facilitate filling the
           line and for isolating the test sections during the test opera-
           tion. See Figure 2 for a typical pressure sectionalizing mani-
           fold. Two-way pigs were loaded at each of the intermediate
           manifolds. The pigs are moved by the fill water and are nec-
           essary to remove the air from the line.
             It is generally a good idea to test the section most distant
           from the water source first. If it should rupture, then testing
           on intermediate sections can continue while repairs on the
           failed section are completed.                             Figure 4. Typical fill site. Courtesy Milbar Hydrotest.
   143   144   145   146   147   148   149   150   151   152   153