Page 150 - Pipeline Rules of Thumb Handbook
P. 150

Hydrostatic Testing  137




































                                    Figure 6. Typical pressure unit set-up. Courtesy Milbar Hydrotest.








           pressure-temperature calculations since the coefficient of  natural gas and certain chemicals are usually dewatered using
           expansion for air is not the same as for water. If the calcula-  compressed air. Care must be exercised in the dewatering
           tions are made and the decrease in pressure cannot be attrib-  operation to make sure that no air is introduced into the test
           uted to a temperature change, then it may be necessary to  section, thus minimizing the possibility of air locks. An air lock
           sectionalize the test section by manifolding and repressuring  is probably the most severe problem involved in dewatering.
           the shorter segments to facilitate locating the leak. Once the  Air locks are caused by air accumulating in the downhill leg
           leak has been located and repaired, testing operations can  and water accumulating in the uphill leg, which creates a
           resume.                                               manometer in the pipeline. In some instances, extremely high
             Air compressors will be required to remove the water once  pressures may be required to overcome the manometer. Care
           the testing is complete. The maximum head for this particu-  should be exercised to be sure the maximum allowable
           lar project was 450 feet (195psig). Allowance will need to be  pipeline operating pressure is not exceeded. It may also be
           included for friction loss in the cross-over manifolds. The  necessary to tap the line and vent air at the high points.
           compressors will need to have sufficient capacity to remove  If it is necessary to pipe the water away from the right-of-
           the water at about the same rate as the fill rate. Most portable  way, welded pipe should be used. The pipe must be securely
           compressors are limited to approximately 125psig. In this  anchored. The use of tractors and skids will probably provide
           case, booster compressors will be needed for the 195 + psig.  sufficient anchoring.
           See Figure 7 for a typical dewatering connection.       Always use a valve to control the amount of water being
             Upon completion of testing, the test pressure is bled off to  bled from the pipeline.
           leave approximately 10 to 20psig at the high point in the test  If there will be a delay in placing the pipeline in operation,
           section. Dewatering may be accomplished using the air com-  and it is decided to leave the test water in the line until
           pressors discussed earlier. Some companies may elect to dis-  operations begin, consideration should be given to the use
           place the test water with the material that will normally be  of a corrosion inhibitor. Long term storage of the line may
           pumped through the line. This is usually the case with crude  necessitate the use of oxygen scavengers in addition to the
           oil and refined product pipelines. Pipelines used to transport  inhibitor.
   145   146   147   148   149   150   151   152   153   154   155