Page 149 - Pipeline Rules of Thumb Handbook
P. 149

136     Pipeline Rules of Thumb Handbook



































                                   Figure 5. Test thermometer placement. Courtesy Milbar Hydrotest.







           The pumps used to fill the line should have sufficient capac-  accept the leakage test if there is no pressure drop in a three
                                        1
         ity to fill the line at a rate of about  / 2 mile per hour. Water  hour period.
         filters should be used and are normally equipped with one  A pressure-volume plot may be required, especially if the
         hundred mesh screens. See Figure 4 for a typical fill site  test pressures approach or exceed the SMYS of the pipe.
         arrangement. Some companies may specify a finer mesh   The plot is made manually during the pressuring operation
         screen. The filling unit should be equipped with a flow meter  by recording pump strokes on the X-axis and pressure on
         to measure the amount of water pumped into the pipeline.  the Y-axis. A straight line will be produced until the plastic
         Temperature recorders will be used to record ambient tem-  range of the pipe is reached or until a leak occurs. This type
         perature, the temperature of the pipe and water, and ground  of plot is also useful should a joint of lighter wall thickness
         temperature. See Figure 5 for typical test thermometer place-  or lower yield strength pipe be inadvertently placed in the
         ment. A pressure recorder will be used to provide a record-  pipeline.
         ing of the pipeline test pressure. A deadweight tester will be  Small leaks during the testing operation can be difficult to
         used to calibrate the pressure recorder. A high pressure pump  locate. A change in the water/pipe temperature may give
         capable of delivering 70 to 150gpm at a pressure exceeding  the appearance of a leak. If the temperature of the pipe/
         the required test pressure will be used in the final pressuring  water decreases, the test pressure will decrease. An increase
         operation. Small high pressure units with a capacity of 6 to   in water/pipe temperature will cause the test pressure to
         30gpm may be used for short sections of large diameter lines  increase. The effect of a temperature change may be esti-
         and smaller diameter lines.                           mated using the equations and data contained in Appendixes
           Deadweight pressure and temperature readings are re-  A and B. To achieve any degree of accuracy in these calcula-
         corded after the prescribed test pressure has been reached  tions, it will be necessary to have accurate temperature and
         and the pressures and temperatures have stabilized. A pres-  pressure readings.
         sure vs. time plot may also be made. Readings are usually  The pipeline test temperature may be affected by river/
         made at fifteen minute intervals for the first hour and at thirty  creek crossings along the pipeline route. Also, if cold
         minute intervals thereafter. The procedure for accepting a  river water is used, there will be a changing temperature
         leakage test will vary from company to company. Some will  gradient. Air, either trapped or entrained, will also affect the
   144   145   146   147   148   149   150   151   152   153   154