Page 238 - Pipeline Rules of Thumb Handbook
P. 238

Corrosion/Coatings  225

           interval potential surveys would seem the most appropriate  of the signal attenuation coating survey. Bearing in mind the
           and perhaps the only survey system to consider.       probably high quality coating of a new pipeline, and because
             Experience has shown however that the repair of signifi-  of the comparison basis employed by the signal attenuation
           cant coating defects will benefit the overall level of cathodic  coating survey, even small coating defects will become readily
           protection achieved, possibly permitting reduction in output  noticeable.
           levels and/or increasing the distance protected from any one  At the other extreme, with poorly coated old pipeline, a
           protection station. In addition, the maintenance of a “two-  Pearson survey may have an almost continuous response
           level” protection system also ensures the highest integrity is  making it impossible to discern individual defects or the most
           maintained for the pipeline. With this purpose in mind, the  significant coating breakdown. The signal attenuation coating
           advantages of the coating surveys become apparent.    survey would, however, be able to give a rapid assessment
             If we consider the requirements of a newly laid pipeline,   of coating condition and indicate where limited rewrapping
           it has been considered important to ensure as near perfect   would be of greatest benefit.
           a coating as is possible at the start of the pipeline”s life. It   In general, therefore, experience has shown that it is cost
           has therefore been common practice to “Pearson” survey the  effective for the more detailed surveys of coating condition
           pipeline after installation. As described above, this survey  and cathodic protection to be undertaken in conjunction with
           requires a two-man team and commonly progresses at some  a signal attenuation coating survey. A number of case histo-
           4–6km per day. This procedure may be accelerated by the use  ries are described below.



           Case histories


             1. Pipeline    : Multiproducts UK                       Survey Period : 10 days—Signal attenuation coating
               Length       : 115 kilometers                                       survey
               Built        : 1982                                                 1 day—Pearson survey
               Coating      : Coal tar reinforced enamel with self-                4 days—Close interval potential survey
                             adhesive tape at field joints.           Survey Results :
               Survey       : Signal attenuation coating survey      Initial signal attenuation coating survey identified 30
               Survey period : 9 days (4 days for disconnection of all  locations of significantly high signal losses, of these 12
                             “temp” magnesium anodes, 5 days for     were attributed to interpipeline bonds and sacrificial
                             survey).                                anodes, the remaining 18 were subject to more detailed
               Survey Results :                                      investigation.
               Survey indicated that over some 80km of the pipeline  Close interval potential surveys showed that a satisfac-
               the coating was satisfactory and further survey work was  tory level of cathodic protection was being achieved at
               not recommended for those areas. Signal losses over   each of the locations where defects had been pinpointed
               these sections ranged between 1.5dB/km and 3dB/km.    using Pearson equipment.
               Some 9 sections, amounting to a total of some 10km    Three particular locations were excavated, in the first a
               were given first priority for further investigation signal  coating defect of some 800mm associated with a welding
               losses were as high as 17.6dB over distances of 1.5km.  arc burn was found within an area previously showing
               A further 2 sections, amounting to some 21km were     a signal loss of 6dB over less than 100m section. In
               classified as second priority items.                   the second area, showing a similar signal attenuation, a
               It was decided that this information gathered be corre-  number of small coating defects were found together
               lated with the results obtained from a proposed intelli-  with a box of welding rods touching the pipe. At the third
               gent pig survey before further action.                location a badly poured bitumen field joint had been
             2. Pipeline    : White Oil products, UK                 indicated by a signal attenuation loss of 10dB.
               Length       : 115 kilometers                       3. Pipeline   : Oil, UK
               Built        : Approx 1963                            Length      : 210 kilometers
               Coating      : Coal tar enamel, tape or bitumen flood  Built       : Approx. 1970
                             field joints                             Coating     : Coal tar enamel with tape wrapped field
               Survey       : Signal attenuation coating                          joints.
                             survey                                  Survey      : Close interval potential survey
                             Pearson survey                                       Recording both “ON” and “OFF”
                             Close interval potential                             potentials at 5 meter intervals.
                             survey                                  Survey period : 40 days for 3 man team
   233   234   235   236   237   238   239   240   241   242   243