Page 43 - Pipeline Rules of Thumb Handbook
P. 43

30    Pipeline Rules of Thumb Handbook

         Flooding for hydrotest


           In order to demonstrate the strength and integrity of   the high points. Even with a pig, in mountainous terrain with
         the pipeline, it is filled with water and pressure tested. The  steep downhill slopes, the weight of water behind the pig can
         air must be removed so that the line can be pressurized effi-  cause it to accelerate away leaving a low pressure zone at the
         ciently because, if pockets of air remain, these will be com-  hill crest. This would cause dissolved air to come out of solu-
         pressed and absorb energy. It will also take longer to bring  tion and form an air lock. A pig with a high pressure drop
         the line up to pressure and will be more hazardous in the  across it would be required to prevent this.
         event of a rupture during the test. It is therefore necessary to  Alternatives to using a pig include flushing out the air or
         ensure that the line is properly flooded and all of the air is  installing vents at high point. For a long or large-diameter
         displaced.                                            pipeline achieving sufficient flushing velocity becomes
           A batching pig driven ahead of the water forms an efficient  impractical. Installing vents reduces the pipeline integrity and
         interface. Without a pig, in downhill portions of the line, the  should be avoided. So for flooding a pipeline, pigging is nor-
         water will run down underneath the air trapping pockets at  mally the best solution.



         Dewatering and drying


           After the hydrotest has been completed, the water is gen-  required for chemical pipelines such as ethylene and propyl-
         erally displaced by the product or by nitrogen. The same argu-  ene pipelines since water will contaminate the material and
         ments apply to dewatering as to flooding. A pig is used to  make it unuseable. After dewatering the pipe walls will be
         provide an interface between the hydrotest water and the   damp and some water may remain trapped in valves and dead
         displacing medium so that the water is swept out of all low  legs. This problem is solved by designing dead legs to be self
         points. A bidirectional batching pig may be used during  draining and installing drain on valves.
         hydrotest and left in the line during hydrotest and then  Refer to Chapter 5, Pipeline Drying, for a detailed dis-
         reversed to dewater the line.                         cussing of pipeline drying methods.
           In some cases, it may be necessary to dry the pipeline. This
         is particularily so for gas pipelines where traces of water   Reprinted with permission—Gulf Publishing Co. “Pipeline Pigging
         may combine with the gas to form hydrates. Drying is also  Technology 2nd Edition”




         Estimate volume of onshore oil spill


           An irregular shape can be converted into a series of rec-
         tangles that approximate the area of the irregular shape.
         There will be about the same amount of spill area outside the
         rectangle as there is dry area inside the rectangle. This can
         be done by stretching a steel tape along the ground outside
         the spill area. The area can then be quickly estimated by
         multiplying the length of the sides. In Figure 1, the following
         area is determined:

         Area A = 70¢¥ 20¢= 1400 square feet
         Area B = 60¢¥ 10¢= 600 square feet
         Area C = 35¢¥ 20¢= 700 square feet

         Total = 2700 square feet

                                                                                     Figure 1
           The more rectangles used, the more accurate the estimate
         becomes.
   38   39   40   41   42   43   44   45   46   47   48