Page 355 - Pipelines and Risers
P. 355

326                                                              Chapter 18

           Pressure, Temperature and Flow Control
          Instrumentation must be provided at the control center to register the pressure, temperature
           and rate of flow in the pipeline. Any variation outside the allowable transients must activate
           an alarm in the control center.


           To ensure protection to the pipeline  against over (and  under,  for example, when  there is
           leakage) pressurization and excessively high temperatures, automatic primary and secondary
          trips should be installed at the compressor station. Details as to their location and their high /
           low pressure and high temperature settings are required as input into the Operations Manual.

           Relief Systems
           Relief systems such as relief valves, are typically required to ensure the maximum pressure of
           the  pipeline  does  not  exceed  a  certain  value.  Relief  valves  must  be  correctly  sized,
           redundancy provided, and they must discharge in a manner that will not cause fire, health risk
           or environmental pollution.


           High Integrity Protective Systems (HIPS) may  be considered when  the conventional relief
           methods  are unsuitable for ultimate plant  protection. However,  the application of  a High
           Integrity Protective System must be justified and its design must be agreed with the relevant
           Regulatory Authority. The following main principles apply:

           0  A clear economic advantage must be  demonstrated over the  conventional approach to
             justify  the increased complexity and dependence on rigorously controlled maintenance
              associated with HIPS;
           0   HIPS  must  be  designed with  appropriate redundancy  and  testing frequency to  ensure
             higher reliability than conventional protection systems;
           0  Economic comparisons should take into account life cycle maintenance and testing costs;
           0  HIPS must respond quickly enough to prevent over pressure if  downstream systems can
             be suddenly blocked-in. This is one reason why HIPS lend themselves to protection of
             large volume systems, including pipelines, rather than small sections of plant;
             HIPS isolation valves must have a tight shut-off. Otherwise, partial capacity relief  valves
              will be needed after the HIPS isolation valves to accommodate leakage rates should the
              HIPS isolation valves fail.


           Leak Detection
           The pipeline must  have an integrity monitoring system capable of  detecting leak.  A  leak
           detection system in  itself has no  effect on  the leak expectancy of  a pipeline  and will only
           make the operator aware of the occurrence of  a leak, enabling him to take remedial actions in
           order to limit the consequences of  the release. The leak detection system requirements will
           vary depending on  the pipeline system in  question  (e.g.  offshore or onshore, length  etc.)
           however, the following should be considered at the design stage and/or implemented during
           operation.
   350   351   352   353   354   355   356   357   358   359   360