Page 377 - Pipelines and Risers
P. 377

348                                                              Chapter 18

          calculated for the both static and dynamic conditions. Accordingly, a “worst case” envelope
          can be developed, which may be used as a basis for designating the allowable span criteria.


          Any spans which exist may be detected by subsequent regular inspection program. The span
          assessment and method of support should also take into account any proposed changes in the
          submerged weight of the pipeline.

          Span  rectification measures  will  have  to  be  employed  if  the  pipeline  span  exceeds the
          allowable span criteria. Generally span rectification measures will take the form of installing
          discrete supports within the length of the unacceptable pipeline span, thus reducing the actual
          freespan length. The installation of an engineered backfill may also be necessary to fill in the
          voids between the supports and to ensure a smooth contour over the pipeline system.

          Before the surface support vessel is mobilized, the repair contractor should, in consultation
          with the Company, propose a design for span  supports and the method of  installing them.
          Design calculations should be undertaken in order that the supports conform to the following
          requirements:


             The supports are positioned such that all relevant spanning conditions of  the pipeline are
             satisfied;
             Realistic installation tolerance is  to  be  included  for  the  horizontal  positioning of  the
             calculated spacing of the supports;
             The  supports are  stable and  fully  support  the  pipeline over  its  remaining design  life
             period;
             The support system is not susceptible to scouring action;
             Lateral movement of the pipeline is prevented by the support installation.


          Supports may be developed by  placing numerous individual sand or grout bags under the
          pipeline. An  alternative to this is to install an empty fabric form-work under the pipeline and
          subsequently fill it with grout. This technique is considered to provide a more reliable and
          complete structural support than by using sand or grout bags and for larger supports may be
          comparatively faster to install. Refer to Figure 18.4. The grouted fabric form-work may be
          shaped to  match  the  contours of  the pipe  and  may  be  provided  with  straps to  ensure a
          permanent connection with the pipeline. Additionally, these units may be designed such that
          during the grouting operation the injection pressure may provide an upward lifting mechanism
          to the pipeline. This feature may provide a useful facility for stress relief in the pipeline span
          if  they  are out with  acceptable limits. Alternatively, if  required, other equipment may  be
          installed to temporarily lift the pipeline during the support installation.
   372   373   374   375   376   377   378   379   380   381   382