Page 483 - Pipelines and Risers
P. 483

450                                                              Chapter 24


          comparison to a single wall flowline. On shore fabrication site requirements will depend on
           system design and local availability of resources.

          Prior  to  offshore  installation,  for  most  pipe-in-pipe  system,  onshore  fabrication  of  the
          individual pipe-in-pipe joints is required. The inner pipe must be placed within the outer pipe
           and  the  annulus filled with  the insulating material,  or the inner  pipe  precoated  with  the
          insulation material must be  slide into the  outer pipe.  The joint  fabrication method would
           depend on the pipe-in-pipe system selected and the installation method and vessel selected.
           As part of  the pipe-in-pipe joint fabrication, the joints could be made up as double, quad or
          hex joints in single operation to suit the installation method.


          Field joint is a critical area for S-lay and J-lay installation. A suitable method that allows the
           welding of pipe joints in a efficient manner that maintains the integrity of the insulation and
           mechanical properties is essential. There are two basic methods available. The first, which is
           more applicable to J-lay is to allow the outer pipe to slide over the inner pipe after the inner
           pipe field weld  has  been  made. The outer pipe is then  welded after the field joint area has
           been insulated with suitable insulating material .t he technique is required and the integrity the
           pipe-in-pipe system during the sliding operation needs to be closely examined. This system
           may not be used for S-lay as the outer pie cannot be slid over the inner pipe in the firing line
           over multiple weld stations.

           242.10 Installation
           Installation Methods
           The total submerged weight of the pipe section suspended in the water column increases as a
           faster rate than  the water depth. A pipe-in-pipe system is generally much  heavier than  its
           single wall counterparts, therefore the tension capacity of  the installation vessel becomes an
           important design factor given the generally low tension capacities of  the existing installation
           vessels available on the market.

           The methods for the installation of  deepwater pipelines are S-lay, J-lay, reeling and towing.
           Detailed accounts on these methods have been made by various authors. A brief summary is
           given here to capture some the key characteristics of each method.


           The S-lay method is tall active with the use of  S-lay vessels with dynamic positioning and
           with stinger capable of  very deep departure angles. With its long firing line and many work
           stations, an  S-lay vessel can  be reasonably productive. Limitations o the use  of  the  S-lay
           technique are  tension  capacity  and  potential  high  strains  in  the  overbend  region,  hence
           restrictions on combination of large pipe diameter and water depth.


           The J-lay method results in a reduction in lay tension requirements. Also, large J-lay vessels
           have  better motion  characteristics and  hence  lower dynamic pipe  stress especially at the
           stinger tip as compared to S-lay. However, productivity can'be low due to limited number of
           work stations and rather confined working space. This shortcoming may be offset somewhat
           by the use of pre-fabricated quad or even hex joints. J-lay is generally not suitable for shallow
           water applications.
   478   479   480   481   482   483   484   485   486   487   488