454                                                              Chapter 24


           24.3.5  Functional Requirement
           Design Pressure
           The general design pressures for the bundle system shall be based on processing data. The
           internal pressure for carrier and sleeve pipes during installation should be at least 1 bar higher
           then the expected water depth.


           Hydrotest Pressure
           Hydrotest pressure of  the  flowlines, heat-up  and  service lines systems shall be  based  on
           1.2xdesign pressure.

           Design Temperature
           Design temperature shall be based on the processing data. Significant temperature drop along
           the bundle system must be avoided.

           Pigging Requirements
           If the bundle system is designed for pigging, the geometric requirement shall be fulfilled. The
           minimum bend radius should be  5 times  the nominal internal diameter of  the pipe to be
           pigged. The pipe shall be gauged as a part of onshore and offshore testing of the system.
           24.3.6  Insulation and Heat-Up System
           The following requirements related to insulation and heat-up functional requirement for the
           bundle system shall be satisfied

              During  normal  operation  the  temperature  shall  be  above  the  hydrate  formation
              temperature for the system.
              Minimum arrival temperature for the production lines shall be  above hydrate formation
              temperature.
              A minimum of certain hours shutdown shall be accepted before the fluid in the production
              lines has reached hydrate formation temperature.
              To melt wax it shall be possible to bring temperature in the system up to above a certain
              degree.


           The cool down  time is the critical factor to determine the bundle insulation requirements.
           Therefore, the design of insulation thickness shall be based on the minimum cool down time.
           The  insulation  combined with  active  heating  shall  fulfil  the  heat-up  requirement  where
           applicable.
           The following factors shall be considered for the bundle thermal design:

              Maximum / minimum operating temperature
              Cool down time
              Heat-up time