Page 186 - Plant design and economics for chemical engineers
P. 186

160  PLANT DESIGN AND ECONOMICS FOR CHEMICAL ENGINEERS
        TABLE 1
        Breakdown of fixed-capital investment items for a chemical process (Continued)
        Direct  Costs
        9.  Land
           Surveys and fees
           Property cost
        Indirect  costs
        1. Engineering and supervision
           Engineering costs-administrative, process, design and general engineering, drafting, cost
            engineering,  procuring,  expediting,  reproduction,  communications,  scale  models,  consultant
            fees, travel
           Engineering supervision and inspection
        2.  Construction  expenses
          Construction, operation and maintenance of temporary facilities, offices, roads, parking lots,
            railroads,  electrical,  piping,  communications,  fencing
          Construction tools and equipment
          Construction  supervision,  accounting,  timekeeping,  purchasing,  expediting
          Warehouse personnel and expense, guards
          Safety,  medical,  fringe  benefits
          Permits, field tests, special licenses
          Taxes,  insurance,  interest
        3. Contractor’s fee
        4. Contingency





        Types of Capital Cost Estimates
        An  estimate of the capital investment for a process may vary from a predesign
        estimate based on little information except the size of the proposed project to a
        detailed estimate prepared from complete drawings and specifications. Between
        these two extremes of capital-investment estimates, there can be numerous
        other estimates which vary in accuracy depending upon the stage of develop-
        ment of the project. These estimates are called by a variety of names, but the
        following five categories represent the accuracy range and designation normally
        used for design purposes:

        1.  Order-of-magnitude estimate (ratio estimate) based on similar previous cost
           data; probable accuracy of estimate over  + 30 percent.
        2. Study estimate (factored estimate) based on knowledge of major items of
           equipment; probable accuracy of estimate up to f30  percent.
        3. Preliminary estimate (budget authorization estimate; scope estimate) based
           on sufficient data to permit the estimate to be budgeted; probable accuracy
           of estimate within +20  percent.
   181   182   183   184   185   186   187   188   189   190   191