Page 215 - Power Quality in Electrical Systems
P. 215

Standby Power Systems  197

        ■ Control: Electronic isochronous governor for independent operation
          and when synchronized to other generators and/or to the utility line.
          Active power load division.
        ■ Generator Protection: Relays to monitor load current, terminal
          voltage, reverse power, frequency, over temperature, to operate alarms
          and trip the circuit breaker.
        ■ Voltage Regulator: Electronic regulator for the exciter or main field
          current to regulate terminal voltage. Reactive power load division.
        ■ Synchronizer: Controls engine speed and circuit breaker closing
          when the E/G set is to operate in synchronism with the utility line
          and/or other E/G sets.
        ■ Circuit Breaker: Electrically operated. Rated for generator over-
          load current and for maximum three-phase short-circuit current.

        Operation. The E/G set is a universal, useful, piece of equipment at a
        site whose output supplements utility service. Its operation includes the
        following functions:

        ■ Loads: Include UPS, lighting, air conditioning, heating, fans, pumps,
          electronic equipment, and appliances. To a degree, loads can draw
          non-sinusoidal current (harmonics) and be unbalanced. The generator
          must have low subtransient reactance (damper windings) and/or be
          oversized for harmonic load current.
        ■ Emergency Operation: The controls of the transfer switch order the
          E/G set to start when an interruption in utility voltage is detected (or
          a manual test signal is entered). When the generator voltage has sta-
          bilized at the correct amplitude and frequency, the transfer switch
          transfers the load to the E/G set. Starting and transfer usually takes
          about 10 s. When utility power is restored, the controls allow the E/G
          set to run for about 30 min before the transfer switch transfers the
          load back to the utility power. Multiple engine-generator sets start in
          sequence.
        ■ Testing: E/G sets for emergency service should be tested about once
          a week, and allowed to run at least 30 min. The generator can be
          loaded with one of the following: (1) a dummy load, (2) a facility load,
          or (3) it can be synchronized to the utility line. The test can be initi-
          ated manually or automatically from a programmable controller.
        ■ Non-emergency Standby: The E/G can be used to provide power to
          equipment or facilities when the normal power source is not avail-
          able—for example, when they are under construction or maintenance
          work is being done. The UPS can be placed on by-pass. Adequate fuel
          must be available.
   210   211   212   213   214   215   216   217   218   219   220