Page 331 - Practical Power System and Protective Relays Commissioning
P. 331

326  Practical Power System and Protective Relays Commissioning


            20.1.2.1 Secondary Injection Tests
            These tests confirm the relay characteristic and check the relay pick-up
            accuracy.


            20.1.2.2 Protection Scheme Function Test
            This test confirms the operation of the relay with other relays, auxiliary
            relays, and other scheme components of protection. This test is done not
            only in the relay panel itself but is also done between the relay panel and
            other relays panels, for example, the busbar protection panel and the feeder
            main-1 protection panels.


            20.1.2.3 Primary Injection Tests

            In these tests the complete system of protection is tested. The operation of
            current transformer (CT), voltage transformer (VT) and protection relays
            also will be tested, for example, checking the stability of the transformer
            differential and restricted earth fault protection by injection 380 V and also
            busbar protection sensitivity and stability tests. These tests are explained in
            the following chapters of this book in detail.


            20.1.2.4 End-to-End Test

            To be done on transmission lines differential protection and distance
            relay telecommunications tripping schemes. These tests need two
            engineers at each end of the line to simulate normal and fault conditions
            and to check the relay response at both ends of the line and also to check
            the decision for tripping the circuit breakers (CBs) at the two ends of
            the line.


            20.1.2.5 On-Load Tests

            These tests are performed after energization of a new circuit and can
            include a directionality test to check that the relay (directional over current
            (OC) relays or distance relays) works in the line direction and not in the
            busbar direction, whilst also checking the operation of line differential
            relays on the load. These load tests are done after opening the tripping links
            of the relay but keeping the circuit protected by another protection on the
            same circuit which the relay under test protects. These tests are explained
            in the following chapters.
   326   327   328   329   330   331   332   333   334   335   336