Substation Testing and Commissioning Time Schedules Chapter | 23  379


                Ten engineers, fifteen technicians, and fifteen laborers are required to
             commission this 500/220/11 kV gas insulated system (GIS) substation with:

                 5 (500 kV bays)       14 (220 kV bays)    20 (11 kV feeders)
                 3 (transformers 500/220 kV)  3 (transformers 220/11 kV)

                The above data are very complicated and need to be carefully managed
             in regard to resources and parallel activities, and coordination with other par-
             ties to the project, such as the project manager, site installation manager,
             subcontractors, and the national electricity control center.