Page 131 - Six Sigma Demystified
P. 131

112        Six SigMa  DemystifieD

                 CHaPTER 5 QUiz


                        1.	 In	developing	a	process	flow	diagram	of	the	current	process,	the	team	should
                           involve
                           a. representatives from each of the process stakeholder groups.
                           B.  only the engineers responsible for designing the process because they know
                             how it’s supposed to be done.
                           C.  only the process personnel because they know how it is actually done.
                           D. only the project sponsor because he or she is paying the bill for the project
                             team’s work.

                        2.	 If	the	baseline	estimates	in	the	measure	stage	do	not	match	the	performance
                           levels	used	to	justify	the	project	in	the	define	stage,	then
                           a. verify that the process personnel conducted the baseline study using the same
                             procedures employed in daily practices.
                           B.  verify the performance levels used to justify the project in the define stage.
                           C.  the differences should be investigated in the analyze stage to determine
                             potential process factors that would replicate the  define- stage behavior.
                           D. all the above should be evaluated.

                        3.	 If	1,000	units	start	a	process	and	100	units	are	scrapped	owing	to	a	total	of
                           300	defects,	the	throughput	yield	of	the	process	is	calculated	as
                           a. 90 percent.
                           B.  70 percent.
                           C.  97 percent.
                           D. 81 percent.

                        4.	 If	1,000	units	start	a	process	and	100	units	are	effectively	reworked	owing	to
                           a	total	of	300	defects,	the	throughput	yield	of	the	process	is	calculated	as
                           a. 90 percent.
                           B.  70 percent.
                           C.  97 percent.
                           D. 81 percent.

                        5.	 A	simple	process	yield	estimate,	calculated	by	dividing	the	number	of	units
                           completing	the	process	by	the	number	of	units	starting	the	process,
                           a. is a simple and effective metric for evaluating the true performance of a
                             process.
                           B.  provides a good indication of the impact of the “hidden factory.”
                           C.  fails to reflect reworks or other corrections internal to the process.
                           D. all the above are true.

                        6.	 If	the	rolled	throughput	yield	for	a		three-	step	process	is	92	percent,	then	an
                           acceptable	target	throughput	yield	for	each	step	of	the	process	is
                           a. 92 percent.
                           B.  81 percent.
   126   127   128   129   130   131   132   133   134   135   136