Page 420 - Six Sigma Demystified
P. 420
400 Six SigMa DemystifieD
Use Options\Parameters for predefined centerline and control limits.
Use Options\Estimate to omit subgroups from the calculations.
Use Options\Stages to define control regions.
Use Options\Test to apply relevant run-test rules.
Excel
Using Green Belt XL Add-On
Use New Chart\U Chart. Specify a constant Subgroup Size or a column contain-
ing variable Subgroup Sizes for each group.
Options
Use Data Range to specify plotted subgroups.
Use Options\Title|Label to set column for x-axis labels.
Use Options\Control Limits for predefined centerline and control limits, to omit
subgroups from calculations, and to define control regions.
Use Options\Analysis\Auto Drop checkbox to automatically remove out-of-
control groups from the control limit calculations (they are still displayed on
the chart).
Use Options\Run Test to apply relevant run-test rules.
Interpretation
The upper and lower control limits indicate the bounds of expected process
behavior. The fluctuation of the points between the control limits is due to the
variation that is intrinsic (built in) to the process. We say that this variation is
due to common causes that influence the process. Any points outside the con-
trol limits can be attributed to a special cause, implying a shift in the process.
When a process is influenced by only common causes, then it is stable and can
be predicted.
If there are any out-of-control points, then special causes of variation must
be identified and eliminated. Brainstorm and conduct designed experiments to
find the process elements that contribute to sporadic changes in process loca-
tion. To predict the capability of the process after special causes have been
eliminated, you should remove the out-of-control points from the analysis,