Page 181 -
P. 181

152           PART TWO  MANAGING SOFTWARE PROJECTS


         FIGURE 6.3
         Risk and      Very high
         management
         concern


                        Impact

                                 Disregard               High
                                 risk factor
                                                          Management
                        Very low                            concern
                             0


                             Probability
                            of occurrence


                                            1.0


                          A project team begins by listing all risks (no matter how remote) in the first col-
                       umn of the table. This can be accomplished with the help of the risk item check-
         Think hard about the  lists referenced in Section 6.3. Each risk is categorized in the second column (e.g.,
         software you’re about  PS implies a project size risk, BU implies a business risk). The probability of occur-
         to build and ask  rence of each risk is entered in the next column of the table. The probability value
         yourself, “What can go
         wrong?” Create your  for each risk can be estimated by team members individually. Individual team mem-
         own list and ask other  bers are polled in round-robin fashion until their assessment of risk probability
         members of the  begins to converge.
         software team to do  Next, the impact of each risk is assessed. Each risk component is assessed using
         the same.
                       the characterization presented in Figure 6.1, and an impact category is determined.
                       The categories for each of the four risk components—performance, support, cost, and
                                           3
                       schedule—are averaged to determine an overall impact value.
                          Once the first four columns of the risk table have been completed, the table is
                       sorted by probability and by impact. High-probability, high-impact risks percolate to
         The risk table is sorted  the top of the table, and low-probability risks drop to the bottom. This accomplishes
         by probability and  first-order risk prioritization.
         impact to rank risks.  The project manager studies the resultant sorted table and defines a cutoff line.
                       The cutoff line (drawn horizontally at some point in the table) implies that only risks
                       that lie above the line will be given further attention. Risks that fall below the line are
                       re-evaluated to accomplish second-order prioritization. Referring to Figure 6.3, risk
                       impact and probability have a distinct influence on management concern. A risk fac-



                       3  A weighted average can be used if one risk component has more significance for the project.
   176   177   178   179   180   181   182   183   184   185   186