13 - PROJECT STAKEHOLDER MANAGEMENT






                   issues or problems. Rarely is “no news” from stakeholders considered to be good news, especially early in a software
                   project. Lack of feedback is more likely a sign of insufficient stakeholder involvement. Efforts should be made to ensure
                   that project stakeholders thoroughly evaluate milestone status, prototypes, and incremental versions of the product.
                   When this does not occur, issues and desired changes may be discovered later in the project when the issues are more
                   costly to fix, or it may be too late to incorporate requested changes while maintaining the delivery schedule.



                   13.3.1 Manage Stakeholder Engagement: Inputs

                      The inputs for managing project stakeholder engagement in Section 13.3.1 of the PMBOK  Guide are applicable
                                                                                                 ®
                   for software projects. In addition, the input in Section 13.3.1.5 is applicable for software projects.


                   13.3.1.1 Stakeholder Management Plan


                                                     ®
                      See Section 13.3.1.1 of the PMBOK  Guide.

                   13.3.1.2 Communications Management Plan

                      See Section 13.3.1.2 of the PMBOK  Guide.
                                                     ®

                   13.3.1.3 Change Log

                      See Section 13.3.1.3 of the PMBOK  Guide.
                                                     ®

                   13.3.1.4 Organizational Process Assets


                      See Section 13.3.1.4 of the PMBOK  Guide.
                                                     ®

                   13.3.1.5 Reviews, Meetings, and Plans

                      Milestone reviews provide opportunities for stakeholder engagement in predictive life cycle software projects.
                   Periodic technical interface meetings (TIMs) can also be held. For software projects that use adaptive life cycles,
                   iteration plans provide an important input for managing software project stakeholder engagement. These plans provide
                   an initial estimate of what will be included in each iterative demonstration or release of the software. Retrospective
                   meetings during each release demonstration provide the opportunity to dynamically update iteration and release plans.



                   13.3.2 Manage Stakeholder Engagement: Tools and Techniques

                      The tools and techniques in Section 13.3.2 of the  PMBOK   Guide are applicable for managing software
                                                                           ®
                   project stakeholder engagement. Sections 13.3.2.4 and 13.3.2.5 of this Software Extension provide additional
                   considerations software projects.