Page 319 - Sustainable Cities and Communities Design Handbook
P. 319

292  Sustainable Cities and Communities Design Handbook


            in energy transition plans. Energy efficiency can help to attenuate demand
            growth and associated GHG emissions. Planning for additional capacity of
            power plants by the CEB or IPPs could thus be delayed, giving breathing space
            to power producers and the economy in terms of capital expenditure and the
            balance of foreign exchange. The current electricity pricing model of the CEB
            does not accurately reflect the financial and environmental costs of generating
            and distributing electricity due to social and economic considerations. In
            these circumstances, energy efficiency and demand side management (DSM)
            opportunities do not receive the same interest that their relevance in the energy
            system mandates. The IEP also underlined the need for additional transmission
            and distribution infrastructure stemming from the operation of a scheme to
            encourage small-scale electricity producers to generate their own electricity
            and sell any excess production or generation to the national grid at preferential
            rates.
               According to the IEP, a new 100-MW coal power plant will be implemented
            with all the mandatory environmental safeguards from 2015 to prevent power
            outages. This decision has sparked protests from environmental organizations
            and residents of the neighborhood of the identified construction site. In
            the wake of the protests, the government set up a NEC to review national
            energy requirements and advise authorities on the planning and execution of
            major projects to address the country’s medium- and long-term energy needs.
            In its report (NEC, 2013), the NEC opined that the IEP of the CEB did not
            comply with the main objective of the LTES, whereby 35% of the total
            electricity generation would be achieved through RE technologies by 2025. The
            NEC also pointed out that it was inconceivable that a plan of such national
            importance was devised without consultations with all stakeholders. Among
            NECs recommendations were its advise to the government to commission an
            additional capacity of 60 MW for an existing power plant running on HFO and
            liquefied natural gas, increase the use of renewable sources of energy, and
            integrate energy efficiency and DSM programs.
               These developments highlight the limitations in the government’s
            deployment plan for RE by 2025. First, the plan focuses only on the electricity
            aspect of the energy consumption. Second, the portfolio of technologies
            consideredisrestrictedanddoesnot takenintoaccount contemporaryalternatives.
            Moreover, it is fraught with inaccuracies. The most obvious one is that the share of
            bagasse-based electricity will be less than the 17% anticipated in the plan due
            to the rapidly decreasing area of land under sugarcane cultivation. As such, the
            focus should be on enhancing the exploitation of readily available RE sources,
            predominantlysolarandwind.ThepotentialofotherabundantREsources,suchas
            tidal and wave, can be tapped in the future but is conditional on resolving some
            uncertainties about the technologies and their cost. More importantly, further
            decarbonization ofthe powergridwillbepossiblethrough significantemphasison
            a more efficient use of the present energy resources and the emergence of
            cost-effective technologies. The next section describes the key enabling
   314   315   316   317   318   319   320   321   322   323   324