Page 315 - Sustainable Cities and Communities Design Handbook
P. 315

288  Sustainable Cities and Communities Design Handbook


               750
                                                   709.8 714.4
               700                         682.6 687.3
                       660.3       655.2 659.2
                               647.3
               650
                           617.7
                   609.4
               600
               550
              MW
               500                                              Effective Capacity
                                                                Peak power demand
                                                       459.9
               450                                 446.2
                                               441.1
                                           430.1
                                       412.5
               400                 404.1
                               388.6
                           378.1
                   367.3 367.6
               350
               300
                     2006  2007  2008  2009  2010  2011  2012  2013  2014  2015
                                     Year
            FIGURE 15.5  Effective capacity and peak power demand for the period 2006e15 (SM, 2015a,
            2016a).


            effective generating capacity of the CEB and IPPs was 714.4 MW (SM, 2015a,
            2016a). Although a reserve margin of more than 50% of the peak load may
            indicate a reliable power system, there are other aspects that need to be
            considered. Several power plants are either nearing their retirement or have
            already exceeded their normal operational lifetimes but have not been phased
            out as their replacements are not ready. In addition, not all IPP plants can
            be operated simultaneously and hydroelectric plants cannot be relied upon
            during summer when peak loads occur because of droughts. As a result, an
            effective reserve margin of 43 MW only is available to address any unforeseen
            generator failure (ADB, 2014a). Even a large margin will be inadequate if a
            major power plant fails unexpectedly. In the next few years, the projected
            increase in peak demand combined with the expected decommissioning
            of some existing generators implies that the CEB must urgently plan for
            generation expansion to mitigate potential shortages in electrical supply.
               Finally, end use data show that the total electricity consumption is
            relatively equally distributed among the domestic, commercial, and industrial
            sectors, as depicted in Fig. 15.6. This distribution contrasts noticeably with the
            disparate distribution of primary energy use among these three end users
            detailed in Primary Energy Requirements section. The manufacturing sector
            accounts for a bigger portion of the primary energy consumption as in addition
            to electricity, it consumes large amounts of fuel for its plant and machinery,
            such as boilers, furnaces, and heat pumps. Households require more primary
   310   311   312   313   314   315   316   317   318   319   320