Page 312 - Sustainable Cities and Communities Design Handbook
P. 312

286  Sustainable Cities and Communities Design Handbook


            producers are also anticipated. Since 2007, the IPPs have overtaken the CEB
            as the major generator of electricity in Mauritius (Elahee, 2011). They have
            maintained this trend since then and generated 59.2% of the total electricity
            needs of the country in 2013. They operate five thermal plants, four of which
            are annexed to sugar mills. One of the IPPs has proposed to import wood chips
            on a trial basis as a greener alternative to coal. The fifth plant runs solely on
            coal on a year-round basis.
               The location of Mauritius just above the Tropic of Capricorn means that

            average daily temperatures around 30 C are common during the hot and
            humid summer season from November to April. During this period, the
            availability of adequate energy sources to cater to the average and peak
            demands for electricity caused by heavy air-conditioning loads (CEB, 2013)
            represents the main challenge for power system planners in Mauritius. The
            load duration curve indicates that the base load, semiload, and peak load for
            Mauritius are, respectively, 170 MW, between 170 and 370 MW, and above
            370 MW, respectively. Contractual agreements between the CEB and IPPs
            presently require CEB to provide for peak and semipeak loads, whereas the
            typically cheaper base load electricity is provided by the IPPs. This scenario is
            not ideal for the CEB as it neither fully exploits its generating capacity nor
            benefits financially. Nevertheless, the urgency to meet the ever-increasing
            demand of electricity led the government to offer financial incentives to the
            IPPs to produce electricity. Concurrently, it represented a unique opportunity
            to exploit a green resource in the form of bagasse for electricity generation.
            The IPPs that owned the sugar factories were thus motivated to invest heavily
            in either new steam generators or upgrade to higher pressure and higher
            temperature boilers and use condensing extraction steam turbines.
               The effective capacities of existing power plants in Mauritius, the types of
            load they serve, and their ownerships are given in Table 15.1. Although the
            total effective capacity of CEB is higher than that of the IPPs, the latter export
            all of their surplus generated electricity to the grid, which serves the base load
            as per the PPAs. The CEB supplies the demand mostly during peak periods,
            implying a low utilization factor. Kerosene-propelled gas turbines are operated
            only during peak times or in case of unexpected breakdowns from other power
            plants as their unit cost of generated electricity is higher. In contrast, the lower
            cost of coal has seen it become the preferable option for serving base loads.
            Thus coal has gradually replaced heavy fuel oil (HFO) in the overall thermal
            electricity production with its share rising from 42% in 2006 to 50% in 2015
            (SM, 2015a, 2016a).
               Fig. 15.5 illustrates that the maximum peak demand has been increasing on
            an average by 3% annually during the period 2006e15, corresponding to an
            effective yearly growth of about 9 MW (SM, 2015a, 2016a). Meanwhile,
            authorities have ensured reliable electrical supply by upgrading the total
            effective capacity to keep pace with the peak demand (SM, 2015a, 2016a). In
            2015, the recorded peak load was 459.9 MW, whereas while the combined
   307   308   309   310   311   312   313   314   315   316   317