Page 223 - Sustainable On-Site CHP Systems Design, Construction, and Operations
P. 223

196    De s i g n


             package and are meant to give utility engineers a general understanding of the pro-
             posed interconnection. The interconnection documents will need to show the CHP gen-
             erator, switchgear, utility feeders, conduit/conductor specifications, and control relays;
             typically, the utility will want to see the same information that a contractor bidding
             the job would need to construct the electrical installation correctly.
                Depending on the interconnection agreement, the utility will also want to see speci-
             fications for some of the electrical equipment. For example, when an automatic transfer
             switch (ATS) is used, perhaps when the plant is used in a standby application, the utility
             will want details on the transfer mechanism. If it is a closed transition ATS, where both
             the utility and CHP generator are connected at the same time for a moment, the utility
             will need to see specifications detailing the synchronization and protection schemes
             between the two feeders. In a similar way, the utility will wish to see details on trans-
             formers (such as impedances) and switchgear.
                Another critical piece of information is a description of the CHP generating equip-
             ment. The interconnection application will indicate the number (and prime mover type)
             of generators being installed and model numbers. It will also ask for electrical informa-
             tion such as
                 •  Nameplate ratings (both kVA and kW). Often, the utility will want the gross and
                    net ratings, with net defined as the difference between gross rating and auxiliary
                    loads used to operate the generator. There may be a significant difference in
                    these values.
                 •  Operating voltage and wiring configuration (single phase or three phase).
                 •  Power factor rating (with adjustment range).
                 •  Grounding system used (solidly grounded or impedance grounded).
                 •  Short-circuit current produced by the generator. This is critical, and can be calculated
                    based on synchronous, transient and subtransient reactance (for a synchronous
                    generator) or locked rotor current (for induction generator).

                Once the electrical designer has provided the utility with all the initial information
             required, the application undergoes an initial review. In this stage, the utility reviews
             the design with an eye to the interconnection agreement (nonexport, incidental export,
             net metering). The certification of the equipment is reviewed. Voltage drop and short-
             circuit current calculations are tested. During this time, an open line of communication
             between the designer and utility is critical to ensure a smooth review process. If the
             CHP generator is relatively small and the utility is satisfied with all of the design param-
             eters, this may be the end of the review and the application would be approved.
                However, there may be a further review required where the generator capacity is a
             greater percentage of the facility load or the interconnection is more complex (such as
             in a network system). The utility will do their own interconnection study, the cost of
             which is usually borne by the CHP facility owner. It is critical that the time and cost for
             this study is built into the project schedule and design budget. If it is not, then the
             economic models used to justify the CHP facility in the first place may not be accurate.

             Final Interconnection Acceptance and Start-Up
             Of course, once a design has been approved and installation of the CHP generating
             facility is underway, it is critical that the installation follows the approved design drawings
   218   219   220   221   222   223   224   225   226   227   228