Page 224 - Sustainable On-Site CHP Systems Design, Construction, and Operations
P. 224

Electrical Design Characteristics and Issues     197


             and equipment specifications. The utility will likely monitor the installation process
             and if the design or equipment selection varies from approved conditions it may trigger
             another utility (and often regulatory agency) review and approval process. As one can
             imagine, this has impacts to schedule and budget. Another potential schedule impact is
             the pretesting which requires temporary (and extensive) paralleling between the CHP
             generator and the utility. Special agreements will likely be necessary and the time taken
             to reach these agreements must be accounted for.
                There are two separate stages to the construction process which ensures a suc-
             cessful switchgear installation in a CHP facility—equipment certification and com-
             missioning. Although it may be a requirement that certification occurs at a third-party
             independent facility, equipment certification is most often done at the switchgear
             manufacturing facility. Just as there are multiple components in a piece of switchgear,
             there are multiple types of certification. One possibility is that each of the components
             has been certified, and then all of the components are combined and tested as an
             assembly. In this case, the switchgear is certified when it leaves the factory as a complete
             system, and the CHP design engineer and facility owner can trust necessary settings
             have been confirmed.
                Another type of certification entails testing all of the components and evaluating
             that each of them performs its particular function. Then, the components are assembled
             as per a previously tested protocol which has proven the components will work together.
             In this case, however, it will be more critical that the connections and settings are tested
             and verified in the field. This testing is a major part of the commissioning process. With
             either method, the switchgear used in a CHP installation will almost certainly require
             special certification by a nationally recognized testing laboratory (NRTL) for intercon-
             nection with the utility.
                Commissioning testing will be the final step in the installation process to assure
             the facility owner that the switchgear will operate as the CHP electrical design
             engineer has intended. Of course, during the installation it is to be expected that
             qualified experienced CHP system contractors run interim tests after each stage of
             the installation, in order to catch and correct issues long before construction is com-
             plete. However, a final testing program will need to be specified which satisfies the
             owner and the utility that the switchgear works as intended, under both normal
             conditions and fault conditions. This testing program must be specific enough to
             note specific components to be tested in each step. For example, the commissioning
             specification might note a specific relay or disconnect which will have to operate to
             ensure an overvoltage condition on a particular downstream feeder does not propa-
             gate to other feeders; that over voltage condition would be simulated as part of the
             commissioning process.


        Sample System Diagram
             There are many possible connection configurations when CHP facilities interconnect
             with a utility. These are dependent on the type of CHP generator, the size of the CHP
             facility, the particular requirements of the serving utility and the type of utility distri-
             bution system. What follows, for reference, is one typical example of the protection
             between utility and CHP facility, and the additional protections typical for engine-
             driven generators.
   219   220   221   222   223   224   225   226   227   228   229