02 (031-048B) chapter 2  1/29/02  4:49 PM  Page 43
                   Data Sources  Due Date Responsibility End Product  3-Jun  Tom  Chart Articles, interviews  5-Jun  Tom  List Facilities management,   interviews  7-Jun  Belinda  Chart management,  Facilities  thrum-mat line super-  visors, interviews  7-Jun  Belinda  List Operations, trade   publications  10-Jun  Belinda  Table Operations,
              Work Plan for Issue in Acme Widgets Issue Tree







                   Analyses  Yes  Technical   Specifications  List of facilities   that meet new   criteria  Map of “facilities  gap”  Sources of required   facilities/equipment  Costs to fill gaps  Effect on project   rate of return










                   Issue/Hypothesis  Can we implement the   necessary changes to the   production process?  Does the new process require   No special facilties?  If it does require special   facilities, can we acquire   Yes


              Table 2-1.                               them?




                                                                         43