Page 52 - The Six Sigma Project Planner
P. 52

Project schedules are developed to ensure that all activities are completed, reintegrated,
                    and tested on or before the project due date. A number of tools and techniques that help
                    create, analyze, and manage project schedules will be discussed next. Software can be
                    used to automate the calculations involved and to make it easier to identify scheduling
                    conflicts and resource shortages. The output of the scheduling activity is a time chart
                    (schedule) showing the start and finish times for each activity as well as its relationship
                    to other activities in the project and responsibility for completing the activity. The
                    schedule must identify activities that are critical in the sense that they must be
                    completed on time to keep the project on schedule.

                    Don’t accept the initial project schedule as a given. The information obtained in
                    preparing the schedule can be used to improve it. Activities that the analysis indicates to
                                                                                  12
                    be critical are prime candidates for improvement. Pareto analysis  can be used to
                    identify those critical elements that are most likely to lead to significant improvement in
                    overall project completion time. Cost data can be used to supplement the time data and
                    the combined time/cost information can be analyzed using Pareto analysis. Always
                    keep in mind that the project’s deadline is a worst acceptable date, not the most
                    desirable.

                    Activity Definition
                    Once the WBS is complete, it can be used to prepare a list of the activities (tasks)
                    necessary to complete the project. Activities don’t simply complete themselves. The
                    resources, time, and personnel necessary to complete the activities must be determined.
                    We now have the information we need to complete this portion of the project plan.

                    Activity Definition Inputs
                    To complete this portion of the project planner, you will need to refer to the WBS (p. 31)
                    and the project charter (p. 2). Additional research will also be required to determine if
                    similar projects or subprojects were conducted previously and, if so, what historical
                    information for activity definitions, activity durations, and problems encountered
                    should be reviewed. Document the findings using Worksheet 14. Historical Research
                    Summary. If available, activity lists from similar projects should be obtained to use as
                    templates. These can be placed into the Planner as supporting detail.
















                    12
                      Six Sigma Handbook, Chapter 8.

                                                             35
   47   48   49   50   51   52   53   54   55   56   57