Page 55 - The Six Sigma Project Planner
P. 55

A common problem to guard against is scope creep. As activities are developed, be
                    certain that they do not go beyond the project’s original scope. Equally common is the
                    problem of scope drift. In these cases, the project focus gradually moves away from its
                    original charter. Since the activities are the project, this is a good place to carefully
                    review the scope statement in the project charter (p. 2) to ensure that the project remains
                    focused on its goals and objectives.


                    Activity Dependencies
                    Some project activities depend on others: sometimes a given activity may not begin
                    until another activity is complete. For example, if the project involves building a house,
                    the construction of the floor cannot begin until the foundation has been poured and had
                    time to cure properly. Other activities can be done in parallel, simultaneously. The
                    outside of the house can be painted while the drywall is being installed inside or while
                    the roof shingles are being installed. The project plan and schedule must take these
                    dependencies into account.

                    To sequence activities so they happen at the right time, you must link dependent
                    activities and specify the type of dependency. The linkage is determined by the nature
                    of the dependency. Activities are linked by defining the dependency between their
                    finish and start dates, as shown below.
                                           Figure 8. Types of Activity Dependencies

                        Activity Dependency Type          Example                   Description

                                                          A                 Activity B cannot start until
                            finish-to-start (FS)                            activity A finishes.
                                                                  B


                                                             A              Activity B cannot start until
                            start-to-start (SS)                             activity A starts.
                                                             B


                                                          A                 Activity B cannot finish until
                            finish-to-finish (FF)                           activity A finishes.
                                                          B


                                                                 A          Activity B cannot finish until
                            start-to-finish (SF)                            activity A starts.
                                                        B







                                                             38