Worksheet 17. Activity Duration Estimates Person Activity Duration Estimates WBS Activity Estimating Description (b) Issue Duration (a) (c) Weighted Most 13 # Optimistic Pessimistic Average Likely 13 Weighted average = (a + 4b + c) / 6. 41