Page 57 - The Six Sigma Project Planner
P. 57

Estimating Activity Duration
                    In addition to knowing the dependencies, to schedule the project you also need
                    estimates of how long each activity might take. This information will be used by senior
                    management to schedule projects for the enterprise and by the project manager to
                    assign resources, to determine when intervention is required, and for various other
                    purposes.

                    Duration Estimation Guidelines
                    It is seldom possible to know the activity duration exactly. A given activity duration
                    estimate can be considered to be associated with a statistical probability of actually
                    achieving it. In most traditional projects, the activity duration is provided by the person
                    to whom the activity is assigned; this person usually includes a buffer that can be used
                    if there are unforeseen, but probable problems. In scheduling and managing projects, it
                    is helpful to know the magnitude of this buffer. Thus, in estimating the duration of
                    activities for Six Sigma projects, we ask for not one but three estimates: optimistic, most
                    likely, and pessimistic. These estimates are defined as follows:
                    Optimistic duration: the activity duration if the work proceeded exactly according to
                    plan, with no delays or interruptions.
                    Most likely duration: the activity duration if we assume a typical pattern of delays and
                    interruptions.
                    Pessimistic duration: the activity duration if we assume an unusually large number of
                    delays and interruptions.
                    In general, duration estimates should be obtained from the person assigned
                    responsibility for the activity. However, if this person is not on the project team, he or
                    she should be made aware of the findings from the research conducted by the team.
                    This would include research into the duration of similar activities on similar projects.

                    Note: In traditional project management, people are asked for deadlines or due dates
                    for their tasks. They are then held accountable for meeting these due dates and
                    punished if they fail to meet them. Under these circumstances, people will always
                    provide pessimistic duration estimates. (Wouldn’t you?) In Six Sigma environments, we
                    develop and manage project schedules based on most-likely estimates or weighted
                    average estimates (explained below). This means that there’s a good chance of not
                    meeting the projected task duration. Thus, although the project schedule must be
                    managed, failure to meet a task duration target must be tolerated. Statistically, the
                    project due date will be met if the average task duration is relatively close to that
                    predicted.











                                                             40
   52   53   54   55   56   57   58   59   60   61   62